,., hobra a Architect & Engineer (B.E.Civil) License No. - STATE/R/2024/APU09610 Contact No. 8793801150 Near Water Tank, Rameshwari, Nagpur Annexure-B ', ,· FORM-2 [See Regulation 3] ENGINEER'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for Withdrawal of Money from Designated Bank Account) Date: 30-06-2025 To, Sai Bhupati Reality, Nagpur. Subject: Certificate of Cost Incurred for Development of "Samrudhi City" having Maha RERA Registration Number P50500078289 (Only applicable after Project Registration) being Developed by Sai Bhupati Reality. Sir, I, Ashish Khobragade _ have undertaken assignment of Certifying Estimated Cost for "Samrudhi City" having MahaRERA Registration Number P50500078289 (Only applicable after Project Registration) being Developed by Sai Bhupati Reality. 1. We have estimated the cost of Civil, MEP and Allied Works required fo� completion of the apartments & proportionate completion of internal & external works of the Project as per the specifications mentioned in the Agreement of Sale. Our estimated cost calculations are based on the Drawings/Plans made available to us for the Project under Reference by the Developers / Consultants. The Schedule of Items & Quantity required for the entire work as calculated by me Quantity Surveyor* appointed by the Developer/Engineer, the assumption of the cost of material, labour & other inputs made by the Developer, and the Site Inspection carried out by us to ascertain / confirm the above analysis given to us. 2. We estimate Total Estimated Cost of completion of the aforesaid Project mentioned under reference at Rs.80,00,000 /- (Total of Table A & B) at the time of Registration. The estimated Total Cost of Project is with reference to the Civil, MEP & Allied Works completion of the apartments & proportionate completion of internal & external works, as per the specifications mentioned in the Agreement of Sale & for the purpose of obtaining Completion Certificate for the Plotted Development from the ____ being the Planning Authority under whose jurisdiction the aforesaid Project is being implemented. 3. The Estimated Cost incurred till date is calculates to Rs 33,05,368.00/- (Total of Table A & B). The Amount of .l;�tlffi?.t�9.�Q§Uf.1.9.IJJI�9.i§.��,��!?.t�9 ..9.n.th�J�_g§jlU�f.if.lP..IJ.t.m?.t�r.i,gJ§ / services used_& unit cost.of.these items. 4. The Balance Cost of completion of the Civil, MEP & Allied Works for completion of Apartments & proportionate completion of internal & external works, as per specifications mentioned in Agreement of Sale, of the aforesaid Project is estimated at Rs. 46,94,632.00 /­ (Total of Table A & 8). 5. I Certify that the cost of Civil, MEP & Allied Work for apartments & proportionate . internal & external works, as per the specifications mentioned in Agreement of Sale, of the aforesaid Project as completed on the date of this certificate is as given in Table A & 8 below: TABLE-A Plotted Development bearing Number P50500078289 or called "Sai BhupatiReality" (to be prepared separately of each Plotted Development of the Real Estate Project) s. Particulars Amount (in Rs.) No. 1. Total Estimated Cost of Building Plotted Rs. 80,00,000 /- Development as on date of Reaistration is 2. Cost incurred as on date of Certificate Rs.33,05,368.00/- 3. Work Done in Percentage (as Percentage of 41.31% Estimated Cost) 4. Balance Cost to be incurred** ((based on Rs.46,94,632.00 Estimated Cost) I- 5. Cost incurred on Additional / Extra Items not included in the Estimated Cost (Table-C) Agreed & Accepted by: Signature of Promoter Firm Name: Sai Bhupati Reality Partner Name: Narayan Dhoble Date: 30-06-2025