Yash Associat es Architects . Engineers . lnteriors Annexure A, FORM 1 [see Regulation 3] ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) oate: { 0, O lt, lO ? 6 To, MIS- LIFESTYLE INFRASTRUCTURE NAGPUR, MAHARASHTRA, 440025 Subject : Certificate of percentage of Work of completion of construction work of Priya Blossoms having MahaRERA Registration Number P50500055967 (Only Applicable after project Registarlion) being developed by MIS. LIFESTYLE INFRASTRUGTURE Sir, l/We YASHWANT POCHALWAR have undertaken assignment as Architect /Licensed Surveyor of certifying Percentage of completion of Construction Work of Priya Btossoms having MahaRERA Registration Number P50500055967 (Only Applicable after project Registration, being developed by M/S. LTFESTYLE INFRASTRUCTURE ) Based on Site lnspection,with respect to Layout I each of the Building/Wing of the aforesaid Real Estate Project I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table A LayouUBuildingMIing Number: Priya Blossoms/NA Sr. No. Tasks/Activity Percentage of Actual Work Done (As on date of the Certificate) (1) tzl (3) I Excavation '100.00 2 Basements (if any) 100.00 3 Podiums (if anv) 0.00 4 Plinth, '100.00 5 Stilt Floor 100.00 6 Slabs of Super Structure 100.00 7 lnternal walls, lnternal plaster, Floorings, Floors and windows within 100.00 Flats/Premises 8 Sanitary Fittinq within the FlaUPremises 90.00 Flat No. 104, KaweriAppt. Ring Road, Narendra Nagar Square, (Shrinagar) Nagpur. Cell:9822721664 Sr. No. Tasks/Activity Percentage of Actual Work Done (As on date of the Certificate) 9 ircases, Iifts Wells and Lobbies at each Floor level Overhead and 100.00 lerground Water Tanks 10 ald..erternal plaster, elevation, completion of terraces with 95.00 11 lnstallation of Lifts, water , Fire Fighting Fittings and Equipment as per 0.00 CFO NOC, Electrical fittinc hanical equipment, compliance to conditions of environmenVCRz NOC, Fi to e_ntrance lobby/s, plinth protection,paving of areas appurtenant to B rg, Compound Wall and all other requirements as may be required to project as per specifications in agreement of Page 2 of 3 Table B 'Common A.rea.s (lnternal and External Development Works) in respect of Registered Phase / Project Number) Sr.No Common areas and facilities ls Available Percentage of Actual Details (Yes / No) Work Done (As on date of the {1t (21 (3) (4) (5) 1 lntqrnal Roads & Footpaths No 0.00 NA 2 Water Supply Yes 85.00 0 J Sewerage (Chamber, Lines, Septic Tank , STp) Yes 65.00 0 4 Storm Water Drains Yes 65.00 0 5 Landscapinq & Tree Plantino Yes 0.00 0 b Street Lighting Yes 0.00 0 7 Qqq!4unity Buildings No 0.00 NA B Treatment And Disposal Of Sewage And Sullaqe Water Yes 0.00 0 I Solid Waste Manaoement And Disoosal Yes 0.00 0 't0 Water conservation /Rain water harvestino Yes 0.00 0 11 Energy managemcnt No 0.00 NA 12 Fire protection and fire safetv reouirements Yes 0.00 0 13 Electrical meter room, sub-station. receivinq station Yes 0.00 U 14 Aggregate area of reqreational Open Space No 0.00 NA 15 Open Parking No 0.00 NA Architects - Engineers - Interiors N.I.T. LIC. No. I tL92l00 Signature & Name (lN BLOCK LETTERS) of L.S/ Architect N,M.C. LIC. No. i357/04 ( License No: 357/04) No. : 442122 Signature of Name: M/s. lnfrastructure Date: ?0, Ol), Xo46 Page 3 of 3