mqnqte DESIGN Architecture Planning & FORM 1 lnteriors [See Regulation 3] ARCHITE CT'S CERTIFI CATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) For Quarter ended 30th September, 2024 Date-7th October,2024 To, M/s Vardan Buildcon, Plot No 2l2,Bajaj Nagar Nagpur-440010 Subject: Certificate of Percentage of Completion of Construction 'Work of Building named "Prerna Harmony" having MAHARERA no. P50500055895, being developed by M/s Vardan Buildcon. Sir, I Lokesh Kadu have undertaken assignment as Architect of Certifying Percentage of Completion of Construction Work of the Project Prerna Harmony, having MAHARERA no. P50500055895, being developed by M/s Vardan Buildcon. Based on the Site Inspection, with respect to the Layout / each BuildingAVing of the aforesaid ReaI Estate Project, I certify that as on date of this Certificate, the Percentage of Work Done for each of the BuildingAVing of the Real Estate Project under MahaRERA is as per Table-A herein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Table-B. 2 TABLE.A Building Prerna Harmony (to be prepared separately for each Building /Wing of the Project) Sr. No. Task/ Activity (2) Percentage (r) of work done (g) 1. Excavation t00% 2. 0 number of Basement(s) and Plinth 100% il. 0number of Podiums NA 4. Stilt Floor 100% 5. 08 number of Slabs of Super Structure 40% 6. Internal Walls, Internal Plaster, Floorings within 0% Flats/Premises, Doors and Windows to each of the Flat/Premises. 7. Sanitary Fittings within the FlatiPremises, Electrical Fittings o% within the FIat/Premises. 8. Staircases, Lifts Wells and Lobbies at each Floor level 0o/o connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9. Staircases, Lifts WeIIs and Lobbies at e:ach Floor leveI o% connecting Staircases and Lifts, Overhead arrd Underground Water Tanks. 10 The external plumbing and external plaster, elevation, 0% completion of terraces with waterproofing of the Building/Wing. 11 Installation of lifts, water pumps, Fire Fighting Fittings and 0% Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, finistring to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/ Wing, Compound Wall and all other requirements as may be required to obtain Occupation / Completion Certificate. : LOKHSH KROU cA/200713€q81 urrndn-+0z,' NIT-z140 TABLE.B Common Areas (Internal & External Development Works) in respect of the Registered Phase / Project Number P50500055895 sl. Common areas and Proposed Percentage Details No. Facilities, Amenities (Yes/No) of Work (s) (r) (g) done Q) (+) 1. Internal Roads &Foot- Yes 50% paths. 2. Water Supplv Yes o% o d. Sewerage (chamber, Iines, Yes o% Septic Tank, STP) 4. Storm Water Drains No NA 5. Landscaping& Tree Yes o% Plantins. 6. Street Lishtine No 7. Community Buildines No 8. Treatment and disposal of No sewage and sullage water 9. Solid Waste management Yes o% Movable & Disposal. Dustbins 10 Water conservation, Rain Yes 50% water harvesting. 11 Enersv management No NA L2 Fire protection and fire Yes o% safety requirements 13 Electrical meter room, sub' Yes 0% Electric Meters station, receivins station. t4 Others (Option to AN No more). ,/ I :. Yours faithtully, re re & Name of Land Surveyor / Arc Signature Kadu Lokesh Kr Ar. LoKE sH il License Number (...... ...C.A/2O6i ,3f1A Agreed &accepted byN tvlCR-402, N lT- 21 40 signature.rfu* Name: Nilesh Mahajan Date: 07'h October 2024