Annexure A FORM 1 (See Regulation 3) ARCHITECT’S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) Date:-25/02/2025 To MUKUNDA KESHAVAM REALTORS KESHAVAM 924, NEAR HALDIRAM, DAY 2 DAY DESHPANDE LAYOUT, NAGPUR-440008 Subject :- Certificate of Percentage of Completion of Construction Work of “MUKUNDA KESHAVAM CITY 9” having MahaRERA Registration Number P50500054443 (Only Applicable after project Registration) being developed by M/S MUKUNDA KESHAVAM REALTORS Sir, I/We PRITI S SHENDE have undertaken assignment as Architect/Licensed Surveyor of certifying Percentage of Completion of Construction work of “MUKUNDA KESHAVAM CITY 9”having MahaRERA Registration Number P50500054443 (Only Applicable after project Registration being developed by M/S MUKUNDA KESHAVAM REALTORS Based on Site Inspection, with respect to Layout/ each of the Building/Wing of the aforesaid Real Estate project . I Certify that as on the date of this certificate, the percentage of Work done for each of the building/wing of the Real Estate Project under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. TABLE-A Layout/Building/Wing Number___________(to be prepared separately for each Layout/Building/Wing of the Project) N.A. Sr No. Tasks / Activity Percentage of Actual Work Done (1) (2) (As on date of the Certificate) (3) 1. Excavation NA 2. Basements (if any) NA 3. Podiums (if any) NA 4. Plinth NA 5. Stilt Floor NA 6. Slabs of Super Structure NA 7. Internal walls, Internal Plaster, Floorings, Doors and windows NA within Flats/Premises 8. Sanitary Fitting within the Flat/Premises NA 9. Staircases. Lifts Wells and Lobbies at each Floor level NA Overhead and Underground Water Tanks 10. External plumbing and external plaster, elevation, NA completion of terraces with waterproofing of the Building/wing, 11. Installation of Lift. water pumps, Fire Fighting Fittings and NA Equipment as per CFO NOC, Electrical fittings, ,Mechanical equipment, compliance to conditions of environment/CRZ NOC. Finishing to entrance lobby/s. plinth protection, paving of areas appurtenant to Building/Wing. Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Any other activities. TABLE-B Sr. No. Common areas and Facilities Proposed Percentage of Actual Details (1) (2) (Yes/No) Work Done (As on date (5) (3) of the Certificate) (4) 1. Internal Roads & Footpaths YES 15% NIL 2. Water Supply YES 15% NIL 3. Sewerage (Chamber, lines, Septic YES 10% NIL Tank, STP) 4. Storm Water Drains YES 15% NIL 5. Landscaping & Tree Planting YES 20% NIL 6. Street Lighting YES 0% NIL 7. Community Buildings NO ---- NIL 8. Treatment and disposal of sewage YES 10% NIL and Sullage water. 9. Solid Waste management & NO ---- NIL Disposal 10. Water conservation / Rain water YES 15% NIL harvesting 11. Energy management NO ---- NIL 12. Fire protection and lire safety NO ---- NIL requirements 13. Electrical meter room, sub-station, YES 10% NIL receiving station. 14. Others (Option to Add more) NO ---- NIL Yours Faithfully, Signature & Name (IN BLOCK LETTERS) of L.S/ Architect (License No. .............) Agreed and Accepted by: Name: M/S MUKUNDA KESHAVAM REALTORS Date: 25/02/2025