B.R.PIPARHETE CONSULTING ARCHITECT & CiVIL ENGINEER. A WING 202, RAJAT SANKUL NEAR GANESHPETH BUS STOP NAGPUR 440012. E-mail:-bhushanpip2023@gmail.com ANNEXURE A FORM1 (SEE REGULATION 3) ARCHITECT'S CERTIFICATE (To be submitted at the time of registration of Ongoing Project and for withdrawal of Money from Designated Bank Account) OCTOBER TO DECEMBER QUARTER 2024 To, Date: 1l6-01-2025 M/S SHIVLAXMILAND DEVELOPERS (Mr. Sanjay Madhukarrao Mahakalkar & Mr. Nandlal S. Sahu, Partners), 97, Ridge Road, Raghuji Nagar Nagpu- 440024 Subject: Certificate of Percentage of Completion of Construction of SHIVANKAR LAYOUT at Kh. No. 64/4 having MahaRERA Registration Number P50500054417 (Only applicable after project registration) being developed by M/sShivlaxmi Land Developers. Sir, I/ We have undertaken assignment as Architect/ Licensed Surveyor of certifying Percentage of Completion of Construction Work of SHIVANKAR LAYOUT at Kh. No 64/4having MahaRERA Registration Number P50500054417 being developed by M/s Shivlaxmi Land Developers. Based on site inspection, with respect to Layout/each of the Building/ Wing of the aforesaid Real Estate Project.. I certify that as on the date of this certificate, the Percentage of Work done for each of the Building/ Wingof the Real Estate Project under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. TABLE A Building- N/A (to be prepared separately for each Building/Wing of the Real Estate Project) SR. Tasks / Activity Percentage of No. (2) Actual Work (1) Done (As on date of the certificate) (3) 1 Excavation NO 2 Basements (if any) NO 3 Podiumns (if any) NO 4 Plinth NO 5 Stilt Floor NO 6 Slabs of super structure NO 7 Internal Walls, Internal Plaster, Floorings, Doors and NO windows within Flats/ Premises Sanitary Fittings within the Flat/ Premises NO Staircases, Lifts wells and Lobbies at each Floor Level NO Overhead and Underground watertanks 10 External Plumbing and External Plaster, elevation, NO completion of terraces with waterproofing of the Building/ Wing 11 Installation of Lifts, water pump, Fire Fighting Fittings and NO Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions of environment/ CRZ NOC, finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/ Wing, Compound wall and all other requirements as may be required to complete project as per specificationsin agreement of sale. Any Other Activities TABLE B Common Areas (Internal and External Development Works)in respect of the Registered Phase / Project Number SR. N0. Common Proposed (Yes Percentage of Details (1) Areas and |No) Actual Work (5) Facilities (3) Done (2) (As on date of the certificate) (4) 1 Internal Road YES 5% NO & Footpaths Water Supply NO NO NO 3 YES 5% Sewerage SEPTIC TANK (Chamber lines, Septic Tank, STP) 4 Strom Water NO NO NO Drains 5 NO Landscaping YES 0% and tree Planting NO 6 Street Lighting YES 0% NO NO NO 7 Community Buildings 5% NO 8 Treatmnent and YES disposal of sewerage and sullage water. NO Solid Waste NO NO Management and Disposal NO 10 Water NO NO Conservation / Rain Water Harvesting NO NO NO 11 Energy Management NO Fire protection NO NO 12 and fire safety requirements Electrical YES 0% NO 13 Meter room, substation, receiving station NO NO NO 14 Others (Option to add more) Yours Faithfully, Signature & Name of Architect BHUSHAN Digitaly signed by BHUSHAN License No: RAJESH RAJESH PIPARHETE PIPARHET Date: 2025.01.21 Agreed and Accepted by: E 13:49:02 +05'30' SHUVLAXMI LAND DEVELOPER SignatuYe of Promoter PARTNER PARTNER Name: Date: 16/01/2025