Annexure A FORM 1 [see Regulation 3] ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) Date:06/10/2025 To, OMKARA BUILDCON NAGPUR, MAHARASHTRA, 440010 Subject : Certificate of percentage of Work of completion of construction work of KRISHNA PRABHA having MahaRERA Registration Number P50500054300 (Only Applicable after project Registartion) being developed by OMKARA BUILDCON Sir, I/We RAVINDRA SONKUSARE have undertaken assignment as Architect /Licensed Surveyor of certifying Percentage of completion of Construction Work of KRISHNA PRABHA having MahaRERA Registration Number P50500054300 (Only Applicable after project Registration, being developed by OMKARA BUILDCON ) Based on Site Inspection,with respect to Layout / each of the Building/Wing of the aforesaid Real Estate Project I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table A Layout/Building/Wing Number: KRISHNA PRABHA/NA Sr. No. Tasks/Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 100.00 2 Basements (if any) 0.00 3 Podiums (if any) 0.00 4 Plinth, 100.00 5 Stilt Floor 100.00 6 Slabs of Super Structure 100.00 7 Internal walls, Internal plaster, Floorings, Floors and windows within 69.00 Flats/Premises 8 Sanitary Fitting within the Flat/Premises 52.00 Page 1 of 3 Sr. No. Tasks/Activity Percentage of Actual Work Done (As on date of the Certificate) 9 Staircases, lifts Wells and Lobbies at each Floor level Overhead and 57.00 Underground Water Tanks 10 External plumbing and external plaster, elevation, completion of terraces with 38.00 waterproofing of the Building/wing. 11 Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per 24.00 CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions of environment/CRZ NOC, Finishing to entrance lobby/s, plinth protection,paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Any other activities. Page 2 of 3 Table B - Common Areas (Internal and External Development Works) in respect of Registered Phase / Project Number) Sr.No Common areas and facilities Is Available Percentage of Actual Details (Yes / No) Work Done (As on date of the Certificate) (1) (2) (3) (4) (5) 1 Internal Roads & Footpaths No 0.00 NA 2 Water Supply Yes 53.00 AS PER PLAN 3 Sewerage (Chamber, Lines, Septic Tank , STP) Yes 63.00 AS PER PLAN 4 Storm Water Drains No 0.00 NA 5 Landscaping & Tree Planting Yes 0.00 AS PER PLAN 6 Street Lighting No 0.00 NA 7 Community Buildings No 0.00 NA 8 Treatment And Disposal Of Sewage And Sullage Water No 0.00 NA 9 Solid Waste Management And Disposal No 0.00 NA 10 Water conservation /Rain water harvesting Yes 61.00 AS PER PLAN 11 Energy managemcnt Yes 24.00 AS PER PLAN 12 Fire protection and fire safety requirements Yes 46.00 AS PER PLAN 13 Electrical meter room, sub-station, receiving station Yes 27.00 AS PER PLAN 14 Aggregate area of recreational Open Space No 0.00 NA 15 Open Parking No 0.00 NA Yours Faithfully RAVINDRA SONKUSARE Signature & Name (IN BLOCK LETTERS) of L.S/ Architect ( License No: CA/1997/22290) Date of Certificate:06/10/2025 Agreed and accepted by: Signature of Promoter Name: OMKARA BUILDCON Date:06/10/2025 Page 3 of 3