DESIGN Architecture Planning & FORM 1 Interiors [See Regulation 3] ARCHITECT'S CERTIFICATE Date: 01/04/2024 For Quarter Ending 31st March 2024 (Qtr.4th F.Y 2023-2024) To. Deovrat Sanjay Jaiswal A-503, Shewalkar Gardens South Ambazari Road, Gopal :-Jagar, Near Vnit Gate, Nagpur - 440022 Subject: Certificate Of Percentage Of Completion Of Construction Work Of 1- Dcv Heights Having Maharera Registration No. P505000513-H Being Developed By Deovrat Sanjay Jaiswal. Sir, I/ We Emanate Design (Architect Lokesh Kadu) Have Undertaken Assignment As Architect /Licensed Surveyor Of Certifying Percentage Of Completion Of Construction Work Of I-Dev Heights, Having Maharera Registration No. P505000513-H Being Developed By Deovrat Sanjay Jaiswal. Based On Site Inspection, With Respect To The Building Of The Aforesaid Real Estate Project , I Certify That As On The Date Of This Certificate, The Percentage Of Work Done For The Building Of The Real Estate Project Under Maharera Is As Per Table A Herein Below. The Percentage Of The Work Executed With Respect To Each Of The Activity Of The Entire Phase Is Detailed In Table B. Block No. 11, llA, 12, 3rd Floor, A-Wing (J.B Wing). Mangalwari Complex, Sadar, Nagpur - 440001 9823872384, 7276384238 emanatedesign9@gmail.com I www.emanatedesign.in Table A Building Number 1-DEV HEIGHTS Sr. No Tasks / Activity l Percentage I of work done 1 Excavation 100% 2 Basements (if any) Nil 3 Podiums (if any) Nil -- Plinth 100% 5 Stilt Floor 100% 6 Slabs of Super Structure 5% 7 Internal walls, Internal Plaster, Floorings, Doors and 0% Windows within Flat/Premises 8 Sanitary Fittings within the Flat/Premises 0% 9 Staircases, Lifts Wells and Lobbies at each Floor level, 0% Overhead and Underground Water Tanks 10 External plumbing and external plaster, elevation, 0% completion of terraces with waterproofing of the Building/Wing 11 Installation of lifts, water pumps, Fire Fighting Fittings and 0% Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Any Other Activities. - Ar. L �