DESIGN Architecture Planning & FORM 1 I n t e r i o r s [See Regulation 3] ARCHITECT'S CERTIFICATE Date: 10/10/2023 For Quarter Ending 30th September 2023 (Qtr. 2nd F.Y 2023-2024) To, DEOVRAT SANJAY JAISWAL A-503, SHEWALKAR GARDENS SOUTH AMBAZARJ ROAD, GOPAL NAGAR, NEAR VNIT GATE, NAGPUR - 440022 Subject: Certificate of Percentage of Completion of Construction Work of 1- DEV HEIGHTS having MahaRERA Registration no. P50500051341 being developed by DEOVRAT SANJAY JAISWAL. Sir, I/ We Emanate Design (Architect Lokesh Kadu) have undertaken assignment as Architect /Licensed Surveyor of certifying Percentage of Completion of Construction Work of 1-DEV HEIGHTS, having MahaRERA Registration no. P50500051341 being developed by DEOVRAT SANJAY JAISWAL. Based on Site Inspection, with respect to the Building of the aforesaid Real Estate Project , I certify that as on the date of this certificate, the Percentage of Work done for the building of the Real Estate Project under MahaRERA is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Block No. II, llA, 12, 3rd Floor, A-Wing (J.B Wing). Hangalwari Complex. Sadar, Nagpur- 4400011 9823872384, 7276384238 I emanatedes1gn9@gma1l.com www.emanatedes1gn.in Table A Building Number 1-DEV HEIGHTS Sr. Tasks / Activity Percentage No of work done 1 Excavation 100% 2 Basements (if an y) Nil 3 Podiums (if any) Nil 4 Plinth 75% 5 Stilt Floor 0% 6 Slabs of Super Structure 0% 7 Internal walls, Internal Plaster, Floorings, Doors and 0% Windows within Flat/Premises 8 San itary Fittings within the Flat/Premises 0% 9 Staircases, Lifts Wells and Lobbies at each Floor level, 0% Overhead and Underground Water Tanks 10 External plumbing and external plaster, elevation, 0% completion of terraces with waterproofing of the Building/Wing 11 Installation of lifts, water pumps, Fire Fighting Fittings and 0% Equipment as per CFO NOC, Electrical fittings, mechan ical equipment, Complian ce to conditions of environment /CRZ NOC, Finishing to entran ce lobby/ s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Any Other Activities. , .r LOKESH KADU Ct--J2007/39381 t-.l\�CR-402, NIT-2140 TABLE-B Common Areas (Internal & External Development Works) in Respect of the entire Registered Phase / Project Number S.No. Common areas and Propos Percentage of Details Facilities, Amenities ed Actual Work (Yes/N done o) (As on date of the certificate) 1 Internal Roads & Footpaths No 0 NA 2. Water Supply Yes 0% NMCWATER AFTER OC 3. Sewerage (chamber, lines, Yes 0% AS PER PLAN Septic Tank , STP) 4. StormWater Drains Yes 0% AS PER PLAN 5. Landscaping & Tree Planting Yes 0% AS PER PLAN 6. Street Lighting No 0 NA 7. Community Buildings No 0 NA 8. Treatment and disposal of No 0 NA sewage and sullage water 9. Solid Waste management & No 0 NA Disposal 10. Water conservation/ Rain Yes 0% AS PER PLAN water harvesting 11. Energy management Yes 0% ASPER PLAN 12. Fire protection and fire safety YES 0% ASPER PLAN Requirement �,�w 13. Electrical meter room, sub- Yes 0% AS PER PLAN I station, receiving station I ' J r. LOKESH KADU C,t.J2007/39381 NMCR-402, NIT-2140 Yours Faithfully Emanate Design (Architect Lokesh Kad ) Name of Architect & Signature Ar. LO SH KADU Agreed and Accepted by: CAI 07/39381 , •�-�CR-402, NlT-2140 Signature of Promoter DEOVRAT SANJAY JAISWAL Place: Nagpur Date:- 10/10/2023