Er. Dhawal Harshe B.E. & D.C.E. (Civil) ~ 9158855005 ~ dhawal.harshe@9mail.com DIVINE PROJECTS Architects. Engineers. Contractors. PP/~3 Annexure A FORM 1 [See Regulation 3) ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project & for.Withdrawal of Money from Designated Account) Date: 09/07/2024 To, M/s PAM Services Nagpur. Subject: Certificate of Percentage of Completion of Construction Work of "Gokul Nagari" having MahaRERA Registration Number P50500051318 being Developed by M/s PAM Services. Sir, I / We Dhawal Harshe have undertaken assignment as ArohiteGt / Licensed Surveyor of Certifying Percentage of Completion of Construction Work of "Gokul Nagari" having MahaRERA Registration Number P50500051318 being Developed by M/s PAM Services. Based on the Site Inspection, with respect to the Layout I eaGh BuildingAAJing of the aforesaid Real Estate Project, I certify that as on date of this Certificate, the Percentage of Work Done for each of the Building/Wing of the Real Estate Project under MahaRERA is as per Table-A herein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Table-B. L,cNo.'41 855005 ~ ·0· . ,__ ~ +.1'/ l litval S~. • ~-~~.,.. 1 .9,, Flit: No. 201, Plot No. J9, C..y4tri Niwcu, Slddticirtti Hagar, 84dt side of Chlntamanf bear, MGnawelda Rfnt ROCld, N~r-2.<4. ------ TABLE-B Common Areas (Internal & External Development Works) in respect of the Registered Phase / Project Number s. Common Areas & Facilities Proposed Percentage Details No. (Yes/ NO) of actual Work Done (As on date of Certificate) (1) (2) (3) (4) (5) 1. Internal Roads & Footpaths Yes 100% Cement Road & pavements 2. Water Supply Yes 100% Borewell & Water line 3. Sewerage (Chamber, Lines, Yes 100% Chamber, lines & STP Septic Tank, STP) -- - 4. Strom Water Drains Yes 100% As per Sanction 5. Landscaping & Tree Planting Yes 100% As per Sanction 6. Street Lighting Yes 100% As per Sanction 7. Community Buildinas NO NA 8. Treatment & Disposal of Sewage NO NA As per Sanction and Sullage Water 9. Solid Waste Management & NO NA - Disposal 10. Water Conservation I Rain Water Yes 100% As per Sanction Harvestina 11. Energy Management No NA 12. Fire Protection & Fire Safety requirements 13. Electrical Meter Room, Sub- Yes 100% As per Sanction Station, Receivina Station 14. Others (Option to Add more) No NA Yours Faithfully License Engineer/ AR~t414Jltl' HSOI DHAWAL S. HARSHE (N.M.R.D.A. Lice (N.I.T ~t~e~rf'!; ( ~ ted by: Signature of Promoter/Joint landowner M/s PAM Services Date: 09-07-2024 2