WRUSHALI PUNWATKAR CIVIL ENGINEER Plot No.490,Ashirwad Nagar, Nagpur - 440024. M. No. 9588414335, Mail: wrushalipunwatkar@omail.com FORM-2 [see Regulation 3] ENGINEER'S CERTIFICATE Dale:29.10.2024 I To M/S. M.KULKARNI BUILDERS and INFMSTRUCTURE PVT.LTD 168, CHHATRAPATI NAGAR, NAGPUR, Subject Certificate of Percentage of Completion of Construction Work of MK- ALTAMOUNT APARTMENTS No. of Building(s)/-ONE Wing(s) of the ONE Phase of the Project [P50500051101- MahaREM Registration Numberl situate on the Plot bearing 9038, KH. NO. 45, CTS. NO. 124, SHEET NO. (25)19-11, HOUSE NO. 350/A/8, MZ-.LENDRA, KHARE TOWN and P. NO. 393/A, KH. NO. 172, CTS NO 12312, SHEET NO. 25119, NMC HOUSE NO. 349, MZ. LENDRA, KHARE TOWN, NAGPUR, demarcated by its to the North-P. NO. 903A, to the South -P. NO. 21to the East- CONSERVANCY LANE to the West- 9.00 M WIDE ROAD of Division- KHARE TOWN, village - DHARAMPETH,Talukaffehsil - NAGPUR District - NAGPURPIN- 440010 ,admeasuring 1023.31 Sq.Mtrs. area being developed by [Promoter's Name- M/S. M.KULKARNI BUILDERS and INFRASTRUCTURE PVT.LTD.] Sir, I WRUSHALI PUNWATKAR have undertaken assignment of certifying Estimated Cost for the Subject. Real Estate Project proposed to be registered under Maha-RERA- P50500051101, being ONE Building(s)/ ONE Wing(s) of the ONE Phase situated on the plot bearing 9038, KH. NO. 45, CTS. NO. 124, SHEET NO. (25)19-11, HOUSE NO. 3s0/A/8, MZ-LENDM, KHARE TOWN and P. NO. 393/A, KH. NO. 172, CTS NO 12312, SHEET NO. 25119, NMC HOUSE NO. 349, MZ. LENDRA, KHARE TOWN, NAGPUR of Division - KHARE TOWN village DHARAMPETH, Taluka/TehsilNAGPUR District NAGPUR. P|N.440010 admeasuring- 1023.31 sq. mtrs. Area being developed by [Promote/s Name- M/S.M.KULKARNI BUILDERS and INFRASTRUCTURE PVT.LTD. 1. Following technical professionals are appointed by Owner / Promoter :- (i) M/siShri/Smt-ABHIJIT AMBADAS ASOLKAR as L.S. / Architect i . (ii) M/s /Shril Smt- PRASHANT Y GHUSHE as Structural Consultant; i (iii) M/s /Shri/ Smt as MEP Consultant; (iv) Mis /Shri/ Smt as Quantity Surveyor. "r,-Wffi-lit'li'T,ri[, BlI' (*;';;';' '-: ' i" "' t 2. we have estimated the cost of the completion to obtain occupation Certificate/ Completion certificate, of the Civit, MEp and Allied works, of the buiHing(s) of the project. Our estimated cost calculations are ,"d" available to us for the project under reference by the Developer and based on the orawingsipianr calculated by - Consultants and the Schedule of items and quantity for the entire work as and the MySELF quantity Surveyof appointed by Developer/Engineer, assumptiffilabourandotherinputsmadebydeveloper,andthesiteinspection carried out by us. 3. We estimate Total Estimated Cost of completion of the building(s) of the aforesaid project under of project is with reference as Rs g330i133.00 (Total of TaulJ n and B). The estimated Total Cost purpose of obtaining reference to the Civil, MEP and allied works required to be completed for the / comptetion certificate toi tne building(s) from theNMC, NAGPUR' being the oicupation certificate Planning Authority under whose jurisdiction the aforesaid project is being implemented. 4. The Estimated Cost tncurred till date is calculated at Rs39114659.O0(Total of Table A and B). The Estimated Cost' amount of Estimated Cost lncurred rs calculated on the base of amount of Total of the subject 5. The Batance cost of Completion of the Civil, MEP and Allied works of the Building(s) Certificate / Completion Certificate from NMC, NAGPUR, (planning Authority) project to obtain Occupation is estimated at Rs-44192 474'00( Total of Table A and B)' as completed on the 6. I certify that the cost of the civil, MEp and allied work for the aforesaid Project date of this certificate is as given in Table A and B below : P TABLEA Building M/ing bearing Number-ONE or called - MK- ALTAMOUNT APARTMENTS (to Ue [t"patiA sepa'rately for each Building /Wing of the Real Estate Project) Particulars Amounts Sr. No. 1 Total Estimated cost of the building/wing as on 25.05.2023 date of Rs 83307133.00. Registration is Rs.39114659 2 Cost incurred as on20.10.2024 (based on the Estimated cost ) 46.95% 3 Work done in Percentage (as Percentage of the estimated cost ) Rs.44192474.00 4 Balance Cost to be lncurred (Based on Estimated Cost) Rs. 00.00 5 Cost lncurred on Additional/Extra ltems as on included in the Estimated Cost (Annexure A) ! -not WEI'*s"sl',' I (3) TABLE B (to be prepared for the entire registered phase of the Real Estate Project) Sr. Particularc Amounts No 1 fotat gstinrated cost of the lnternal and External Development Works including Rs. amenitiesandFacilitiesinthelayoutason-dateofRegistrationis 83307133.00 /- 2 Cost incurred as on Rs. (based on the Estimated cost ) 39114659.00/- 3 Work done in Percentage 46.95% (as Percentaqe of the estimated cost ) 4 Balance Cost to be lncurred Rs. (Based on Estimated Cost) 44192474.4U- 5 Cost lncurred on Additional/Extra ltems as on not included in Rs. 00.001 the Estimated Cost (Annexure A) Yours Faithfully Signature of Engineer - Wrushali Punwatkar * Note 1. The scope of work is to complete entire Real Estate Project as per drawings approved from time to time so as to obtain Occupation Certificate /Completion Certificate. 2. (.) Quantity survey can be done by office of Engineer or can be done by an independent Quantity I Surveyor, whose certificate of quantity calculated can be relied upon by the Engineer. ln case of 1 independent quantity surveyor being appointgd by Developer, the name has to be mentioned at the place . marked (*) and in case quantity are being cdlculated by office of Engineer, the name of the person in the ; office of Engineer, who is responsible for the quantity calculated should be mentioned at the place + marked (*). 3. The estimated cost includes all labour, material, equipment and machinery required to carry out entire work. 4. As this is an estimated cost, any deviation in quantity required for development of the Real estate Project will result in amendment of the cost incurred/to be incurred. 5. All components of work with specifications are indicative and not exhaustive. I Annexure A ! List of Extra / Additional ltems executed with Cost (which were not part of the original Estimate of Total Cost) wfr*r{ho{. WRUSHALI PUNWATKAR BE (Civil), M Tech (StructuralEngg.)