VIKESH MESHRAM Engineer, planner & Interior Designer Office - Plot No. - 15, Cosmos Town jaitala Road, Nagpur- 440022. Mob. - +91-7350882026 VIKESH MESHRAM Form 2 [See Regulation 3] ENGINEER'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account -Project Wise) To, Date:31-12-2023 SHRIKEDARESHWAR BUILDERS & DEVELOEPRS PVT. LTD. 5 &6, "Shreerath" near G.H. Raisoni School, Hingna Road, Subhash Nagar, Nagpur-440036 Subject: Certificate Of Cost Incurred for Development of RENUKA RENAISSANCE having MahaRERA Registration Number P50500006452 being developed by SHRI KEDARESHWAR BUILDERS & DEVELOPERS PVT. LTD. 'for the Quarter Ending Decemnber 2023. Sir, I Vikesh Meshram have undertaken assignment of certifying Estimated Cost for Project Name having MahaRERA Registration Number P50500006452 Being developed SHRI KEDARESHWARBUILDERS &DEVELOPERS PVT. LTD. 1 Ihave estimated the cost of the Civil, MEP and Allied works required for completion of the apartments and proportionate completion of internal & external works of the project as per specifications mentioned in agreement of sale. Our estimated cost calculations are based on the Drawings/plans made available to us for the project under reference by the Developer / Consultants and the Schedule ofitems and quantity for the entire work as calculated by JITENDRA INGULKAR Quantity Surveyort appointed by Developer / Engineer, and the assumption of the cost of the cost material, labor and other inputs made by developer, and the site inspection carried out by us to ascertain / confirm the above analysis given to us. 2 Iestimate Total Estimated Cost of completion of the aforesaid project under reference at Rs. 96,61,58,707 at the time of Registration.The estimated Total Cost of project is with reference to the Civil, MEP and allied works required for completion of apartments and proportionate completion of internal &external works, as per specifications mentioned in agreement to sale and for the purpose of obtaining occupation certificate / completion certificate for the Building(s) / Wing(s) / Layout / Plotted Development from the Nagpur Municipal Corporation being the Planning Authority under whose jurisdiction the aforesaid project is being implemented. 3. TheEstimated Cost Incurred tilldate is calculated at Rs.79,79,75,578. The amount of Estimated Email :vikeshmeshram75@gmail.com Cost Incurred isalculated basedon input materials / services used & unit cost of these items. The Balance cost of Completion of theCivil. MEP and Allied works for completion of the apartment and proportionate completion of internal &external works,as per specifications mentioned in agreement to sale of the Project is estimated at Rs. 16,81,83,129. 5 ICertify that cost for the Civil / MEP / Allied Work for the apartment and proportionate completion of internal &external works, as per specifications mentioned in agreement to sale, of the aforesaid Project as completed on the date of thiscertificate is as given in Table Aand B below. Table A Building / Wing / Layout/Plotted Development bearing Number P50500006452 or called RENUKA RENAISSANCE (To be prepared separately for each building / wing / Layout / Plotted Development of the Real Estate Project) Sr. No. Particulars Amount (In Rs.) 1 Total Estimated Cost of Building/ Rs.96,61,58, 707 Wing / Layout/ Plotted Development As On Date Of Registration is 2 Cost Incurred As On 31-12-2023 Rs. 79,79,75,5 78 3. Work Done In Percentage 82.59% (As Percentage Of Estimated Cost) 4 Balance Cost To Be Incurred Rs. 16,81,83,12 9 (Based on Estimated Cost)** 5 Cost Incurred In Additional/ NIL Extra Item not included in the Estimated Cost (Table - C) Table B Internal & External Development Works in Respect of the Registered Phase Sr. No. Particulars Amounts 1 Total Estimated Cost of the Internal and NA external Development Works including amenities and facilities in the layout as on date of Registration is 2 Cost Incurred As On 31-12-2023 NA 3. Work Done In Percentage NA (As Percentage Of Estimated Cost) 4. Balance Cost To Be Incurred (Based on NA Estimated Cost) 5. Cost Incurred InAdditional /Extra Item NA not included in the Estimated Cost (Table -C) Yours Faithfully, Agreed and accepted by Shri Kedareshwar Builders & Developers Private Limjted Signature VIKESH MESHRAM Director ENGINEER NIT/BE(W)/4678/511 Note: 1 The scope of work is to complete Registered Real Estate Project as per drawings approved from time to time and as per specifications mentioned in agreement of sale. 2. (") Quantity survey can be done by ofice of Engineer or can be done by an independent Quantity Surveyor, whose certificate of quantity calculated can be relied upon by the Engineer. In case of independent quantity surveyor being appointed by Developer, the name has to be mentioned at the place marked (*) and in case quantity are being calculated by office of Engineer, the name of the person in the office of Engineer, who is responsible for the quantity calculated should be mentioned at the place marked () 3. ("*) Balance Cost to be incurred (4)may vary from Difference between Total estimated cost(1) andActual Cost incurred (2) due to deviation inquantity required / escalation of cost etc. As this estimatedcost, any deviation in quantity required for development of the Real Estate Project will result in amendment of thecost incurred / to be incurred. 4. All the components of work with specifications are indicative and not exhaustive. 5. Please specify if there are any deviations / qualifications. Example: Any deviation in input material used from specifications in agreement of sale. Table C List of Extra /Additional /Deleted Items considered in Cost (Which were not part of the original estimate of Total Cost) Sr. No. List of Extra/ Amount (In Rs.) Additional/ Deleted Items NIL