I FORM 1 [,geeRegulation 3] ARCHITECT'SCERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) For the quarter ended on 31" March, 2019 Date: 31" May, 2019 To, Badjate Real Estate Pr,t. Ltd., Shop no.01 & 02, Sant gadge Maharaj Dharamshala, Medical Square, Nagpur 400010 Subject Certificate of percentage of Completion of Construction Work of "City center-2" project p50500003869 for the Construction of one commercial Building situated on the Plot [Maha RERA No. No. X=102/2 admeasuring about 6,144 sq. mtrs., of Mouza Rengapar, within the limits of Nagpur Municipal Corporation & Nagpur Improvement Trust, Butibori, MIDC, Tahsil & District - Nagpur demarcated by its boundaries as below, being developed by M/s Badjate Real Estate Pvt. Ltd. On the East: Plot no. X-70213 On the West: Plot no. X-102/l On the North:Road On the South: Plot no. X-102/4 Sir I/ We have undertaken assignment as Architect /Licensed Surveyor of certifying Percentage of Completion of Construction Work of the One Building of the Project "Cify center-2", Building situated on the plot No. X-702/2 admeasuring about 6,144 sq. mtrs., of Mouza Rengapar, within the limits of Nagpur Municipal Corporation & Nagpur Improvement Trust, Butibori, MIDC, Tahsil & District - Nalpur demarcated by its boundaries as below, being developed by M/s Badjate Real Estate Pvt' Ltd; 2 On the East: Plot no. X-102/3 On the'W.est: Plot no. X-102/l On the North:Road On the South: PIot no. X-I02/4 1. Following technicai professionals are appointed by owner / Promoter :- i. Shri Bhavik M. |ain as Architect ii. M/s. P. T. Mase & Associates as Structural Consultant iii. Shri Anil sakhare as a Site Supervisor I Based on Site Inspection, with resPect to each of the BuildingflVing of the aforesaid Real of Work done Estate project, I certify that as on the date of this certificate, the Percentage for each of the buildingfl\ring of the Real Estate Project as registered vide . P50500003869 number under Maha RERA is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in the Table B TABLE-A Building Aying Number 01 (to be prepared separately for each Building AVing of the Project) Sr. No. TasV Activity (2) Percentage of (1) work done (3) 1 Excavation 100o/o 2 01 number of Basement(s) and 1 Plinth 100o/o 3. ... number of Podiums NA 4. Stilt Floor NA 5 04 number of Slabs of Super Structure 35o/o 6 Internal Walls, Internal Floorings within Plaster, 10o/o Flats/Premises, Doors and Windows to each of the Flat/Premises. 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings 0o/o within the FlaVPremises. 3 8. Staircases, Lifts Wells and Lobbies at each Floor level 20o/o connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, elevation, 0o/o completion of terraces with waterproofing of the BuildingAVing. 10 Installation of lifts, water Pumps, Fire Fighting Fittings and 0o/o Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /cRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas aPPurtenant to Building/ wing, compound wall and all other requirements as may be required to obtain Occupation / Completion Certificate. TABLE-B Internal and external Development'Works in respect of the entire Registered Phase' sl. Common areas and Facilities, Proposed Percentage of Details No. Amenities (YesA'{o) Work done (s) (1) (3) (4) t. Internal Roads & Foot- ths. No 2. Water Su Yes 0o/o 3. Sewerage (chamber, lines, Yes 0o/o Tank, STP) 4. Storm Water Drains No Yes 0o/o 5 Landscaping & Tree Planting. No 6. Street No 7, Community Buildings No 8. Treatment and disposal of and water No 9. Solid Waste management & 4 Disposal. 10 Water conservation, Rain water Yes 0o/o 11 No 12 Fire protection and fire safetY Yes 0o/o 13 Electrical meter room, sub- Yes 70o/o station, receiving station. 14 Others (Option to Add more). Yours Faithfully, C^^n AVIK $ffi. JAIru Signature & Name (IN BLOCK LETTERS) of L.S/ Architect (License No. CA/20 1 7 / 82531)