FORM-2 lsee Regulation 3l ENGINEER'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account- Project wise) Date: To The Pyramid Ashok Megastructures Private Limited, Pyramid City-6, Besa Pipla Road, Mouza- Pipla, Nagpur - 440037. Subject : Certificate of Percentage of Completion of Construction Work of 4 No. of quilding(s)/ 6 Wing(s) of the 1't Phase of the Project lMaha RERA Registration Numberl situated on the PIot bearing Khasara No. 155/4 & 156/6 of Division Nagpur village Pipla taluka Nagpur (Rural) District Nagpur PIN rt40037 admeasuring 21200 sq.mts. area being developed by Pyramid Ashok Megastructures Private Limited. Sir, I Mnod Mahato have undertaken assignment as Architect /Licensed Surveyor of certifying Percentage of Completion of Construction Work of the 4 Building(s)/ 6 Wing(s) of the 1"'Phase of the Project, situated on the plot bearing Khasra. No. 155/4 & 156/6 of Division Nagpur village Pipla taluka Nagpur (Rural) District Nagpur PIN 440037 admeasuring 21200 sq.mts. area being developed by IPromoter's Name] 1. Following technical professionals are appointed by Owner / Promoter :- (i) M/s/Shri/Smt Sanjay Soni as L.S. / Architect ; (ii) M/s /Shri / Smt Ravindra Karendekar as Structural Consultant (iii) M/s /Shri / Smt Nitn Khirwadkar & Abhinav Nikam as MEP Consultant (iv) M/s /Shri / Smt Rinkesh Rao as Site Supervisor 2. We have estimated the cost of the completion to obtain Occupation Certificate/ Completion Certificate, of the Civil, MEP and Allied works, of the Building(s) of the project. Our estimated cost calculations are based on the Drawings/plans made available to us for the project under reference by the Developer and Consultants and the Schedule of items and quantity for the entire work as calculated by quantity Surveyor* appointed by Developer/Engineer, and the assumption of the cost of material, labour and other inputs made by developer, and the site inspection carried out by us. 3. We estimate Total Estimated Cost of completion of the building(s) of the aforesaid project under reference as Rs 379631621 (Total of Table A and B). The estimated Total Cost of project is with reference to the Civil, MEP and allied works required to be completed for the purpose of obtaining occupation certificate / completion certlficate for the building(s) from the NMRDA being the Planning Authority under whose iurisdiction the aforesaid project is being implemented. 4. The Estimated Cost Incurred till date is calculated at Rs. 379631621 (Total of Table A and B)-. The amount of Estimated Cost Incurred is calculated on the base of amount of Total Estimated Cost. 5. The Balance cost of Completion of the Civil, MEP and Allied works of the Building(s) of the subject project to obtain Occupation Certificate / Completion Certificate from NMRDA (planning Authority) is estimated at Rs 0 ( Total of Table A and B). 6. I certify that the Cost of the Civil, MEP and allied work for the aforesaid Project as completed on the date of this certificate is as given in Table A and B below : TABLE A Building Numberl,2,3 & 4 (to be prepared separately for each Building /wing of the Real Estate Project) Sr. No. Particular Amounts I Total Estimated cost of the building/wing as on Rs.305524800 281712017 date of Registration is 2 Cost incurred as on 28107120'17 Rs 305524800 (based on the Estimated cost ) 3 Work done in Percentage 1Q0 o/o (as Percentage of the estimated cost ) 4 Balance Cost to be Incurred Rs. 00 (Based on Estimated Cost) 5 Cost Incurred on Additional /Extra ltems Rs. 00 as on 2810712017 not included in the Estimated Cost (Annexure A) TABLE B (to be prepared for the entire registered phase of the Real Estate Project) Sr Particulars Amounts No 1 Total Estimated -cost of the Internal and External Rs. 74106821 r Development Works including amenities and Facilities in the layout as on 2810712017 date of Registration is 2 Cost incu rred as on 28107 12017 Rs.74106821 (based on the Estimated cost ) 3 Work done in Percentage 100 o/o (as Percentage of the estimated cost ) 4 Balance Cost to be lncurred Rs. 0/- (Based on Estimated Cost) 5 Cost lncurred on Additional iExtra ltems as on 28107120'l'7 KS. U/- not included in the Estimated Cost (Annexure A) -Vin"d b. t{"h"ho Signature of Engineer (Licence No.............) r Note 1. The scope of work is to complete entire Real Estate Project as per drawings approved from time to time so as to obtain Occupation Certificate /Completion Certificate. 2. (*) Quantity survey can be done by office of Engineer or can be done by an independent:euantity Surveyor, whose certificate of quantity calculated can be relied upon by the Engineer. ln case of independent quantity surveyor being appointed by Developer, the name has lo be mentioned at the place marked (*) and in case quantity are being calculated by office of Engineer, the name ofthe person in the office of Engineer, who is responsible for the quantity calculated should be mentioned at the place marked (.). 3. The estimated cost includes all labour, material, equipment and machinery required to carry out entire work. 4. As this is an estimated cost, any deviation in quantity required for development of the Real estate Project will result in amendment of the cost incurred/to be incurred. 5. All components of work with specifications are indicative and not exhaustive. Annexure A List of EXra / Additional ltems executed with Cost (which were not part of the original Estimate of Total Cost)