Ar. SAN|AY SONI Architect, lnterior Designer, Planner Shri Rishabh Appt, 10/304 Ganesh Nagar, Near S.D. Hospital Nagpur, Mobile - 7507544662 FORM 1 lsee Regulation 3l ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) Date: 28107120'17 To The Pyramid Ashok Megastructures Private Limited, Pyramid City-6, Besa Pipla Road,:Mouza- Pipla, Nagpur - 440037. Subject : Certificate of Percentage of Completion of Construction Work of 4 No. of Building(s)/ 6 Wing(s) of the 1"t Phase of the Project lMaha RERA Registration Numberl situated on the Plot bearing Khasara No. 155/4 & 156/6 of Division Nagpur village Pipla taluka Nagpur (Rural) District Nagpur PIN 440037 admeasuring 21200 sq.mts. area being developed by Pyramid Ashok Megastructures Private Limited. Sh, I Sanjay Soni have undertaken assignment as Architect /Licensed Surveyor of certifying Percentage of Completion of Conslruction Work of the 4 Building(s)/ 6 Wing(s) of the l"tPhase of the Project, situated on the plot bearing Khasra. No. 155/4 & 156/6 of Division Nagpur village Pipla taluka Nagpur (Rural) District Nagpur PIN 440037 admeasuring 21200 sq.mts. area being developed by Ipromoter's Name] 1. Following technical professionals are appointed by Owner / Promoter :- (i) M/s/Shri/Smt Sanjay Soni as L.S. / Architect ; (ii) M/s /Shri / Smt Ravindra Karendekar as Structural Consuttant (iii) M/s /Shri/ Smt Nitn Khirwadkar & Abhinav Nikam as MEP Consultant (iv) M/s /Shri / Smt Rinkesh Rao as Site SuDervisor Based on Site Inspection, with respect to each of the BuildingArVing of the aforesaid Real Estate Project , I certify that as on the date of this certiflcate, the Percentage of Work done for each of the buildingruing of the Real Estate Project as registered vide number under Maha RERA is as oer table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table A Building - 1, Tower- A. Sr Tasks /Activity Percentage of No work done 1 Excavation 100% 2 One number of Plinth 100% 3 Zero number of Podiums 0 4 Stilt Floor 100% 5 Nine number of Slabs of Suoer Structure 10oo/o 6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors 100% and Windows to each of the FlauPremises 7 Sanitary Fittings within the FlavPremises, Electrical Fittings within the 100% FlaVPremises 8 Staircases, Lifts Wells and Lobbies at each Floor level connectino 't00v. Slaircases and Lifts, Overhead and Underground Water Tanks 9 The extemal plumbing and external plaster, elevation, completion of 100% terraces with waterproofing of the Building/Wing, 10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as 100% per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to BuildingMing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate ffi Building - 1, Tower- B. Sr Tasks /Activity Percentage of No work done 'l Excavation 't00% 2 One number of Plinth 100% 3 Zero number of Podiums 0 4 Stilt Floor 100% 5 Nine number of Slabs of Suoer Structure 100% o Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors 100% and Windows to each of the FlavPremises 7 Sanitary Fittings within the FlavPremises, Electrical Fittings within the 100% FlaVPremises 8 Staircases, Lifts Wells and Lobbies at each Floor level connectinq t00% Staircases and Lifts, Overhead and Underground Water Tanks 9 The external plumbing and external plaster, elevation, completion of 1000/, terraces with waterproofing of the BuildingMing, 10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as 100% per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant lo Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate *%'!ffi;;,,"5 i \-r'ur r-s'? ' , 3 Building - 2, Tower- C. Sr. Tasks /Activity Percentage of No work done 1 Excavation 't00% 2 One number of Plinth 't00% 3 Zero number of Podiums 0 4 Stilt Floor 'l 00% c Nine number of Slabs of Suoer Structure o Internal walls, lnternal Plaster, Floorings within Flats/Premises, Doors 100% and Windows to each of the FlavPremises 7 Sanitary Fittings within the FlaUPremises, Electrical Fittings within the 100% FlaVPremises 8 Staircases, Lifts Wells and Lobbies at each Floor level connecting 100% Staircases and Lifts, Overhead and Underground Water Tanks 9 The external plumbing and external plaster, elevation, completion of ,t00% terraces with waterproofing of the BulldingMing, 10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as 100o/o per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipmenl, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate Building - 2, Tower- D. Sr. Tasks /Activity Percentage of No work done 1 Excavation 100% 2 One number of Plinth 100% 3 Zero number of Podiums 0 Stilt Floor 100% 5 Nine number of Slabs of Super Structure 100%' o Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors 100% and Windows to each of the Flat/Premises 7 Sanitary Fittings within the FlaUPremises, Electrical Fittings within the 100o/o FlaUPremises 8 Staircases, Lifts Wells and Lobbies at each Floor level connecting 100% Staircases and Lifts, Overhead and Underground Water Tanks I The external plumbing and external plaster, elevation, completion of 100% terraces with waterproofing of the Building/Wing, 10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as 1O0o/o per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/vving, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 6f"*S y 121t3oorrsaaz)a ("kq, Building - 3, Block- A Sr. Tasks /Activity Percentage of No work done 1 Excavation 100% 2 One number of Plinth 100% 3 Zero number of Podiums 0 4 Stilt Floor .t00% 5 Two number of Slabs of Super Structure ,1000/o 6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the FlavPremises 7 Sanitary Fittings within the FlaUPremises, Electrical Fittings within the 100% FlaVPremises 8 Staircases,and Lobbies Overhead and Underground Water Tanks 100% o The external plumbing and external plaster, elevation, completion of 100% terraces with waterproofing of the BuildingMing, 10 Water pumps, , Electrical fittings to Common Areas Finishing to entrance 100% lobby/s, plinth protection, paving of areas appurtenant to BuildingMing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate Building - 4, Block - B Sr. Iasks /Activity Percentage of No work done 1 E