SKAC O N S oRTI M Architecture Engineering Project Management Consultants INDIA. Phone: +91-712-2245333 01, RPTS Road, Laxminagar, Nagpur 440 022 (M.5) E-mail: skaconsortium@gmail.com +91-712-2221082 Fax: +91-712-2221082 ARCHITECT'S CERTIFICATE Date:27.01.2021 To The Adisun Buildcon Pvt.Ltd, 0-1,RPTS Road, Laxmi Nagar, Nagpur-440 022, Subject: Cetificate of Percentage of Completion of Construction Work of 1(one) No. of Building(s) 1(One) Wing(s) of the First Phase of the Project [MahaRERA Registration Number situated on the Plot bearing C.N. No.10/CTS No. /Survey no. 193 Final Plot no. 26 demarcated by its boundaries (latitude and longitude of the end points) 21 07 15.47N to the North 79 02 29.51F to the South 21 07 15.84N to 79 02 30.64E the East 79 02 29.98F to the West of Division Nagpur, village Nagpur taluka Nagpur District Nagpur PIN 440 022 admeasuring 540 sq.mts. area being developed by [Promoter's Name Sir, / We SKA Consortium have undertaken assignment as Architect /Licensed Surveyor of certifying Percentage of Completion of Construction Work of the ADISUN AVENUE Building(s) 1(ONE) Wing(s) of the Phase of the Project, situated on the plot bearing C.N. No/CTS No. 193/Survey no. Final Plot no 26 of Division Nagpur village Ngpur Taluka Nagpur, District Nagpur PIN 440 022 admeasuring 540 sq.mts. area being developed by [Adisun Buildcon Pvt.Ltd ] 1. Following technical professionals are appointed by Owner/ Promoter (0 M/s/Shri/Smt Ar.Vijay Salankar (SKA Consortium)as L.S. / Architect () M/s /Shri/ Smt Er P.S.Patankar (Patankar Consultants Pvt.Ltd) as Structural Consultant (ii) M/s/Shri/Smt Er. N.M. Deshkar( Technodeal Consultants) as Electrical/MEP Consultant (iv) M/s/Shri/Smt Rajshekhar Joshi as Site Supervisor Based on Site Inspection, with respect to each of the Building/Wing ofthe aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project as registered vide number . under MahaRERA is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. TABLE-A Building/Wing Number 01 (to be prepared separately for each BuildingWing of the Project) Sr.No Tasks/Activity Percentage of work done Excavation 100% 01 Number of Basement(s) and Plinth 100% 3. .....number of Podiums N.A ....Stilt Floor N.A 5. 5 Numbers of Slabs of Super Structure 40% Internal walls, Internal Plaster, Floorings within 0%( Yet to Start) Flats/Premises, Doors and Windows to each of the Flat/Premises Sanitary Fittings within the Flat/Premises, | 0%( Yet to Start) Electrical Fittings within the Flat/Premises 8. Staircases, Lifts Wells and Lobbies at each Floor 10% level connecting Staircases and Lifts, Overhead and Underground Water Tanks 9 The external plumbing and external plaster, 0%( Yet to Start) elevation, completion of terraces with water proofing of the BuildingWing 10. Installation of lifts, water pumps, Fire Fighting 0%( Yet to Start) Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electromechanical equipment, Compliance to conditions of environment/CRZ NOC, Finishing to entrance lobby/s, plinth protection paving of areas appurtenant to Building/MWing, Compound Wall and all other requirements as may be required to obtain Occupation/Completion Certificate TABLE-B Internal& External Development Works in Respect of the entire Registered Phase Sr.No Common areas and Proposed Percentage of Details Facilities, Amenities (Yes/No) work done . Internal Roads & Foot N.A. N.A N.A. paths Water Supply Yes 0% 0%( Yet to Start 3. Sewerage (chamber, lines, | Yes Yes 0%( Yet to Septic Tank, STP) Start) Storm Water Drains Yes 0% 0%( Yet to 5. Start) Landscaping& ree Yes 0% 0%( Yet to Planting Start) Street Lighting Yes N.A N.A Community Buildings No N.A N.A 8. Treatment and disposal of Yes N.A N.A sewage and sullage water 9 Solid waste management | Yes N.A N.A and Disposal 10 Water conservation, Rain Yes 0% 0% Yet to water harvesting Start 11 Energy Management Yes N.A N.A |12 Fire protection and fire Yes | 0% 0% Yet to start safety requirements 13 Others (Option to Add more) Yours faithfully For SKA Consortium CONSC /SCA/T8/4376 CA78/4306 RT CA/98/23483/ AR.VIJAY SALANKAR PARTNER License No.NMC/R-288