Planners Varsl "bsignars CreaLios 221, Tukdoji Nagar, Manewada Road, Nagpur. Cell : 7743884370, 9763411194 ngineers CATI/230/ 2016-17 STATE /R/ 2023 / APL /05491 ARCHITECT'S CERTIFICATE Date-20/10/2024 To, The (ADITYA PRATAPVIR BAHADUR SHAH) Project Name- RAJE VIR BAHADUR SHAH LAYOUT Ramdaspeth, Nagpur Subject: Certificate of Percentage of Completion of Development Work up to 30.09.2024 situated at Khasara No.: 107, 108, 109, 110 at, Mouza-Mahurzari „Nagpur (Rural), Nagpur, 441501 Nagpur having Maha RERA Registration Number P50500021448 being developed by [ADITYAPRATAP VIR BAHADUR SHAH] Sir, Surveyor of certifying I/ We Parag P. Urade have undertaken assignment as Architect /Licensed SHAH VIR BAHADUR LAYOUT having Percentage of Completion of Development Work of RAJE being MahaRERA Registration Number_ P50500021448 (Only Applicable after project registration) developed by ADITYA PRATAP VIR BAHADUR SHAH Real Estate Project, I certify that as on the Based on Site Inspection, with respect to the aforesaid the entire Real Estate Project under Maha date of this certificate, the Percentage of Work done for the work executed with respect to each of RERA is as per table A herein below. The percentage of the activity of the entire phase is detailed in Table B. GREA PLANNERS DESIGNERS ENGINEERS & GOVT. APPRGVED) VALUER WAGPU PANEL VALUER 2 State Bank of Indig Bank of India Ltd., Nagpur. Nagvel Nagri Sahakari Patsanstha * Repco Home Finance Lid. Shikshak Sahakari Bank itd.. Nggpur, Architectural Sevices * Building Planning With Sanctioning * Estimating Valuation Supervision TABLE-B Internal & External Development Works in Respect of the entire Registered Phase S. No Common areas and Facilities, Proposed Percentage Details Amenities (Yes/No) of Work done 1 Internal Roads & Footpaths YES 85% Not completed 2 Water Supply YES 20% Not completed 3 Sewerage (chamber, lines, YES 70% Not completed Septic Tank, STP) 4 Storm Water Drains YES 30% Not completed 5 Landscaping & Tree Planting YES 00% Not completed 6 Street Lighting YES 00% Not completed 7 Community Buildings NO 8 Treatment and disposal of YES 00% Not completed sewage and sullage water 9 Solid Waste management & NO Disposal 10 Water conservation, Rain NO water harvesting 11 Energy management NO 12 Fire protection and fire safety NO requirements 13 Electrical meter room, sub NO station, receiving station 14 Others (Open space) YES 40% Not completed ATIO ADUR PLANERS DESIGNERS ENGINEERS& GOVT.APPROVED VALUER A PARAG P. URADE Consulting Archltecturai VAGPUR Designer & Govt.Approved Valu