FORM 1 [see Regulation 3] ARCHITECT'S CERTIFICATE Date: 02/04/2020 To, SADESH REALTY BUILDERS LLP, House No. 897, Shivnarayan Bhawan, P S Agrawal Marg, Santra Market, Near Hanuman Temple, Nagpur-440018(MH) Subject: Certificate of Percentage of Completion of Construction Work of DIVINE CITY-II having MahaRERA Registration no. P50500020052 being developed by Sadesh Realty Builders LLP. Sir, I/We Architect Kalyani Adhau have undertaken assignment as Architect/Licensed Surveyor of certifying Percentage of Completion of Construction Work of DIVINE CITY-II, having MahaRERA Registration no. P50500020052 being developed by Sadesh Realty Builders LLP. Based on Site Inspection, with respect to the building of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the building of the Real Estate Project under MahaRERA is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table A DIVINE CITY-II Sr. Tasks /Activity Percentage No of work done 1 Excavation NA 2 Basements (if any) NA 3 Podiums (if any) NA 4 Plinth NA 5 Stilt Floor NA 6 Slabs of Super Structure NA 7 Internal walls, Internal Plaster, Floorings, Doors and NA Windows within Flat/Premises 8 Sanitary Fittings within the Flat/Premises NA 9 Staircases, Lifts Wells and Lobbies at each Floor level, NA Overhead and Underground Water Tanks 10 External plumbing and external plaster, elevation, NA completion of terraces with waterproofing of the Building/Wing 11 Installation of lifts, water pumps, Fire Fighting Fittings and NA Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Any Other Activities. TABLE-B Common Areas (Internal & External Development Works) in Respect of the entire Registered Phase / Project Number S.No. Common areas and Propos Percentage Details Facilities, Amenities ed of (Yes/N Actual Work o) done (As on date of the certificate) 1 Internal Roads & Footpaths Yes 15% As Per Plan 2. Water Supply Yes 12% As Per Plan 3. Sewerage (chamber, lines, Yes 4% As per Plan Septic Tank, STP) 4. Storm Water Drains Yes 0% As Per Plan 5. Landscaping & Tree Planting Yes 0% As Per Plan 6. Street Lighting Yes 0% As Per Plan 7. Community Buildings No 0 NA 8. Treatment and disposal of Yes 0% As Per Plan sewage and sullage water 9. Solid Waste management & No 0 NA Disposal 10. Water conservation/ Rain Yes 0% As Per Plan water harvesting 11. Energy management No 0 NA 12. Fire protection and fire safety No 0 NA Requirement 13. Electrical meter room, sub- Yes 0% As Per Plan station, receiving station Yours Faithfully Architect Kalyani Adhau Name of Architect & Signature Agreed and Accepted by: Signature of Promoter Dilip Pralhadrai Agrawal Partner/Authorized Signatory SADESH REALTY BUILDERS LLP Date: 02/04/2020