R.D. ARCHITECTCTS & CONSULTANT'S Near Ground , Laxmi Nagar, Nagpur. Cell No:- 9422110416 LIC No. CA /2000 / 26055 FORM 1 [See Regulation 3] ARCHITECT' SCERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) 1 For Quarter ending 31' March 2018 Date09 thApril, 2018 To, Raghuveer Constructions, B-306, Pritam Complex, Old Bhandara Road, Bagadganj, Nagpur 440008 Subject: Certificate of -Percentage of Completion of ConstructionWork of'Shivarpan" project [Maha RERA No. P50500001454 for the Construction of one Residential Building/ Nil Wings named Shivarpanofthe Mis Raghuveer Constructions situated on the Plot no. 2, Dubey layout, Jaitala Road,Nagpur 440036, demarcated by its boundaries as below, Taluka & Diskict: Nagpur, Maharashtra, Pin 440008, admeasuring 459.73 Sqmtr. area being developed by Mis Raghuveer Constructions. On the East : Plot No 1 & 6 On the West: Road & Plot no 3 On the North :Road & Plot no 1 On the South : Plot No 6 & 7 Sir, V We Rahul Deshpande have undertaken assignment as Architect /Licensed Surveyor of certifying Percentage of Completion of Construction Work of the One Building of the Project "Shivarpan" , situated on the plot bearing Plot no. 2, Dubey layout, Jaitala Road,Nagpur 440036 demarcated by its boundaries as below, Taluka & District : Nagpur, Maharashtra , Pin 440008admeasuring 459.73 Sqmtr . Area being developed by 1\11/s Raghuveer Constructions On the East : Plot No 1 & 6 On the West : Road & Plot no 3 On the North :Road & Plot no I On the South : Plot No 6 & 7 1. Following technical professionals are appointed by Owner / Promoter :- (i) Shri Rahul Deshpande 11s Architect (ii) Shri P. Y. Ghushe as Structural Consultant (iii) Shri Sanjay Gupta as a Site Supervisor l I 2 Based on Site Inspection, with .respect to each of the Building/Wing of the aforesaid Real Estate Project, f certify r that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project as registered vide P5050000 \ 454number under MahaRERA is as pet table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in the Table B TABLE-A Building /Wing Number 0l(to be prepared separately for each Building /Wing of the Project) Task/ Activity (2) Percentage of Sr. No. work done (3) (1) Excavation 100% 1. 0 number ofBasement(s) and l Plinth 100% 2. 3. 0 number of Podiums - 4. Stilt Floor 100% 5number of Slabs of Super Structure 100% 5. 6. Internal Walls, Internal Plaster, Floorings within Flats/Premises, Doors 100% and Windows to each of the Flat/Premises. 7. Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 80% Flat/Premises. 8. Staircases, Lifts Wells and Lobbies at each Floor level connecting 85% Staircases and Lifts, Overhead and Underground Water Tanks. The external plumbing and external plaster, elevation, completion of 85% 9 terraces with waterproofing of the Building/Wing. JO Installation of lifts, water pumps, Fire Fighting Fittings and Equipment 70% as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas· appurtenant to Building/ Wing, Compound Wall and all other requirements as may be required to obtain Occupation / Completion Certificate. TABLE-B Internal and external Development Works in respect of the entire Registered Phase. Common areas and Facilities, Proposed Percentage of Details SI. No. Amenities (Yes/No) Workdone (5) (1) (2) (3) (4) I. Internal Roads&Foot-paths. No - 2. WaterSuoply Yes 100% 3. Sewerage (chamber, lines, Septic Yes 100% Tank, STP) 4. Storm WaterDrains No - No - 5. Landscaping& Tree Planting. 6. Street Li ghting No No . - - 7. Community Buildings No 8. Treatment and disposal of sewage - and sullage water No 9. Solid Waste management & - Disposal. 10 Water conservation, Rain water Yes 100% harvesting. 11 Energy manae:ement No - 12 Fire protection and fire safety No - requirements 13 Electrical meter room, sub-station, Yes 70% receiving station. 14 Open Parking Yes 100% .· i i:- Signature & Name (INC BL~C: LE~E~S) ofL.S/ Architect. ( ,,, , / K • ,, ·p -' C"l; - -~ - , I \ /