Flat no 4, Vipul Apartment, Saraswati Vihar, Trimurti Nagar, Nagpur- 440022 email: trimitnagpur@gmail.com M: +91 9325416475 www.trimitarch.com \ Annexure A FORM 1 [See Regulation 3] ARCHITECT’S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project & for Withdrawal of Money from Designated Account) Date :26-07-2022 To, Mr. Rajkumar R Deshmukh Sau Sangita P Rithe Partner in Maa Vaishnavi Builders & Developers Wardha Subject: Certificate of Percentage of Completion of Construction Work of “Maa Vaishnavi Nagari - 9” having MahaRERA Registration Number P50400024971 being Developed by Rajkumar R Deshmukh, Sau Sangita P Rithe (Partner in Maa Vaishnavi Builders & Developers). Sir, I Ar. Priya Choudhary have undertaken assignment as Architect / Licensed Surveyor of Certifying Percentage of Completion of Construction Work of “Maa Vaishnavi Nagari - 9” having MahaRERA Registration Number P50400024971 being Developed by Shri. Rajkumar R Deshmukh, Sau Sangita P Rithe (Partner in Maa Vaishnavi Builders & Developers). Based on the Site Inspection, with respect to the Layout / each Building/Wing of the aforesaid Real Estate Project, I certify that as on date of this Certificate, the Percentage of Work Done for each of the Building/Wing of the Real Estate Project under MahaRERA is as per Table-A herein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Table-B. Layout / Building / Wing Number __ (to be prepared separately for each Layout/Building/Wing of Project) S. No. Tasks / Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1. Excavation 100% 2. Basements (if any) 100% 3. Podiums (if any) NA 4. Plinth 100% 5. Stilt Floor 100% 6. Slab of Super Structure 100% 7. Internal Walls, Internal Plaster, Floorings, Doors, windows 100% within Flats / Premises 8. Sanitary Fittings within Flats / Premises 100% 9. Staircases, Lift Wells & Lobbies at each Floor Level Overhead 100% and Underground Water Tanks 10. External Plumbing & External Plaster, Elevation, Completion of 100% Terraces, with waterproofing of the Building / Wing 11. Installation of Lifts, Water Pumps, Fire Fighting Fittings and 100% Equipments as per CFO NOC, Electrical Fittings, Mechanical Equipments, Compliance to conditions of Environment / CRZ NOC, Finishing to Entrance Lobby/s, Plinth Protection, Paving of Areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete Project as per specifications to Agreement of Sale, Any other Activity TABLE-B Common Areas (Internal & External Development Works) in respect of the Registered Phase / Project Number S. No. Common Areas & Facilities Proposed Percentage Details (Yes / NO) of actual Work Done (As on date of Certificate) (1) (2) (3) (4) (5) 1. Internal Roads & Footpaths Yes 100% 2. Water Supply Yes 100% 3. Sewerage (Chamber, Lines, Septic Yes 100% Septic Tank for first Phase Tank, STP) 4. Strom Water Drains Yes 100% 5. Landscaping & Tree Planting Yes 100% 6. Street Lighting Yes 100% 7. Community Buildings No Second Phase 8. Treatment & Disposal of Sewage and Yes 100% Sullage Water 9. Solid Waste Management & Disposal Yes 100% 10. Water Conservation / Rain Water Yes 100% Harvesting 11. Energy Management Yes 100% 12. Fire Protection & Fire Safety Yes 100% requirements 13. Electrical Meter Room, Sub-Station, Yes 100% Receiving Station 14. Others (Option to Add more) 15. Aggregate area of recreational Open Space Yours faithfully, Agreed & Accepted by: Signature of Partner Name: Shri. Rajkumar R Deshmukh Date: 26/07/2022