ROHIT PUNSHI Cape design studio ARCHITECT B.ARCH.,MBA 3] FORM 1 [see Regulation ARCHITECT'S CERTIFICATE Registration of Ongoing Project and for (To be submitted at the time of Building/Wing wise) withdrawal of Money from Designated Account - Date : 07/ 10/2024 To, Vasavi Lifespaces Private Limited Subject: Certificate of Percentage of Completion of Construction Work of: MIDAS Enciave having MahaRERA No. P50300076783 being developed by Vasavi Lifespace Pvt Ltd as on (30/09/2024) Sir, I/ we Rohit Punshi have undertaken assignment as Architect/ Licensed Surveyor of certifying Percentage of Completion of Construction work of MIDAS Enclave having MahaRERA No. P50300076783. Based on Site Inspection, with respect to Layout/each of the Building / Wing of the aforesaid Real Estate Project. Icertify that as on the date of this certificate, the Percentage of Work done for each of the building / Wing of the Real Estate Project under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table A separately for each Building Building /Wing Number Wing A(to be prepared /Wing of the Project) Percentage Sr. Tasks |Activity of No work done 41.03 % 1 Excavation Onumber of Basement(s) 3 O number of Podiums 0% 4 8 number of Slabs of Super Structure 5 Internal walls, Internal Plaster, Floorings within o% Flats/Premises, Doors and Windows to each of the Flat/Premises 6 Sanitary Fittings within the Flat/Premises, Electrical 0 % Fittings within the Flat/Premises 7 Staircases, Lifts Wells and Lobbies at each Floor level O% connecting Staircases and Lifts, Overhead and Underground Water Tanks The external plumbing and external plaster, elevation, 0% completion of terraces with waterproofing of the Building/Wing Installation of lifts, water pumps, Fire Fighting Fittings and 0 % Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE-B Internal & External Development Works in Respect of the entire Registered Phase S.No. Common areas and Proposed Percentage Details Facilities, Amenities (Yes/No) of Work done NA NA 1 Internal Roads &Footpaths No Borewell and 2. Water Supply Yes 0% Pump installed Yes 0 % As per Plan 3. Sewerage (chamber, lines, Septic Tank , STP) No NA 4 Storm Water Drains 5 No NA Landscaping &Tree Planting No NA 6. Street Lighting 7. Electrical meter room, sub Yes 0 % As per Plan station, receiving station 8. Aggregate area of recreational No NA Open Space 9. Open Parking No NA 10. Community Buildings No NA 11. Treatment and disposal of No NA sewage and sullage water 12. Solid Waste management && No NA Disposal 13. Water conservation, Rain water Yes 0% As per Plan harvesting 14. Energy management No NA 15. Fire protection and fire safety No NA requirement 11. Others ( Option to Add more) No NA YoursFfithfully intorior Desicner C.. ig. No CA/0003s080 ROHIT PUNSHI (Architect) rohitpunshi @ gmail.com,contact : +91 9403419559, 12, Subhash Colony, AMRAVATI -444 606 (M.S.) Agreed and accepted by: Signature of Promoter Name: Vasavi Lifespaces Pvt Ltd Date: 08/01/2025