FORM 1 ARCHITECT'S CERTIFICATE for withdrawal of Money from (To be submitted at the time of Registration of Ongoing Project and Designated Account- Building/Wing wise) Date: 07/07/2023 To, Sky Line Builders and Developers, Amravati Tower having Subject: Certificate of Percentage of Completion of Construction Work of: Galaxy MahaRERA No. P50300048524 being developed by Sky Line Builders and Developers, Sir, / we ABDUL HASAB ABDUL HAKAM have undertaken assignment as Architect/Licensed Surveyor of certifying Percentage of Completion of Construction' work of Galaxy Tower having MahaRERA No. PS0300048524. Based on Site Inspection, with respect to Layout/each of the Building/ Wing of the aforesaid Real Estate Project. I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table-A Layout/Building/Wing Number (To be prepared separately for each Building /Wing of the Project) SrNo Tasks / Activity Percentage of Actual Work Done (1) (2) (As on date of the Certificate) 1 Excavation 80 2 Basements (if any) 20 3 Number of Podiums (if any) Plinth Work Dóhe Percentage of Actual Tseke / Activitv 0 Stilt Floor 2 slabs of super structure 6 5 Floorings within 7 Internal walls,Internal Plaster, to each of the Flats/Premises, Doors and Windows Flat/Premises 8 Sanitary Fittings within the Flat/Premises. Floor level 10 9 Staircases, Lifts Wells and Lobbies at each connecting Staircases and Lifts, Overhead and Underground Water Tanks 10 External plumbing and external plaster, elevation, 0 completion of terrace with the waterproofing of the building. 11 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC,Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and allother requirements as may be required to Obtain Occupation /Completion Certificate TABLE- B Common Areas (Internal and External Development Works) in respect of the Registered Phase/ Project Number S. No. Common Roads and Facilities, Amenities Proposed Percentage of Work Details (Yes/No) done 1 Internal Roads & Foothpaths 2 Water Supply s pen Yes 2 O 3 Sewerage (chamber, sewage lines), Storm Water Drains Yes pla Storm Water Drains 22 5 Landscaping &Tree Planting 6 Street Lighting 7 Community Building Treatment and disposal of sewage N and sullage water 9 Solid Waste management & Disposal No 10 Water conservation, Rain water p harvesting Yes Plan 11 Energy management No 12 Fire protection and fire safety requirements Yes 13 Electrical meter room, sub-station, receiving station ND 14 Other Yours Faithfully KAHEKASHA ARCHITECIS AR A80UI HASAG ABJLAA& Signature &Name (IN BLOCK LETTERS) of L. S. / Architect (License no. ... Agreed and Accepted by: Signature of Promoter Name: Sleikh kos Skyline Buiders And Developers Date: 07/07/2023. Partner