S.R.Infrastructure Shashank.R.Chandak M.Tech (C.M), VJTI, Mumbai B.E (Civil), VIIT, Pune Mob. :8080364755, 8275418699 Ref. No. Date : FORM -2 ENGINEER'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account - Project wise) Date: 10/04/2025 To, The Chandak Construction, Amravati -444601. Subject: Certificate of Cost Incurred for Development of Chandak Tower having MahaRERA Registration Number P50300051204 being developed by Chandak Construction (As on 31.03.25) Sir, Shashatk.R. Uhandak we ...have undertaken assignment of certifying Estimated Cost for Chandak Tower having MahaRERA Régistration Number P50300051204 being developed by Chandak Construction. 2 We have estimated the cost of Civil, MEP and Allied works required for completion of the lapartments and proportionate completion of internal &external works of the project as per bpecificatons mentioned in agreement of sale. Out estimated cost calculations are based on the prawing/plans made available to us for the project under reference by the Developer Consultants. The Schedule. of times and quantity required for the entire work as calculated by Shashank R. Chandak Licensed Engineer appointed by Developer/ Engineer, the assumption of the cost offmaterial, labour and other inputs made by developer, and the site inspection carried out by us to ascertain/confirm the above analysisgiven to us. 3. Welestimate Total Estimated Cost of completion of the aforesaid project under reference as Rs. 1,2p.5D,000/- (Totalof Table Aand B) at the time of Registration. The estimated Total Cost of project is with reference to the Civil, MEP, and allied works required completion of the apartments and propotionate completion of internal & external works, as per specifications mentioned in agreerment of sale and for the purpose of obtaining occupation certificate / completion certificate for the buildingls)/Wingls)/Layout/Plotted Development from the Amravati Municipal Corporation being thie Planning Authority under whose jurisdiction the aforesaid project is being implemented. Çhandak Bungalow, Near Govt. Girls High School, Camp Road, Amravati. Maharastra. - 444 602 4. The Estimated Cost Incurred till date is calculated at Rs.1,61,72,267/-. The amount of Estimated Cost Incurred is calculated on the basis of input materials/services used and unit cost of these items. 5. The Balance cost of Completion of the Civil, MEP and Allied works for completion of the apartments and proportionate completion of internal & external works, as per specifications mentioned in agreement of sale, of the Project is estimated at Rs -39,22,267/ 6. Icertify that the Cost of the Civil, MEP and allied work for the apartments and proportionate internal &external works, as per specifications mentioned in agreement of sale, of the aforesaid Project as completed on the date of this certificate is as given in Table A and B Below. TABLE -A Building called Chandak Tower Sr. No. Particulars Amounts Total Estimated cost of the building as on date of Registration is Rs 1,22,50,000/ 2 Cost incurred as on date of certificate Rs 1,61,72,267/ 3 Work done in Percentage (as Percentage of the estimated cost) 132.02% Balance Cost to be Incurred** (Based on Estimated Cost) Rs -39,22,267/ 5 Cost Incurred on Additional / Extra Items not included in the Estimated Cost (Table-C) Rs TABLE-B Internal & ExternalDevelopment Works in Respect of the Registered Phase Sr. No. Particulars Amounts 1 Total Estimated cost of the Internal and External Development Works including amenities and Rs Facilities in the layout as on date of Registration is 2 Cost incurred as on date of certificate Rs 3 Work done in Percentage (as Percentage of the estimated cost) % Balance Cost to be Incurred (Based on Estimated Cost) Rs 5 Cost Incurred on Additional/ Extra Items not included in the Estimated Cost (Table-C) Rs Yours Faithfully Signature of Engineer Propretor (Licence No..mL335%.) Local Authority License no. Agreed and accepted by: P M/s ÇHANDAR CORSTROONCE Signature of Promoter Name: Najgopal J. Chaua avcl DilipATAdak Date: 0 -04- 202G Note: approved 1. The scope of work is to complete Registered Real Estate Project as per drawings from time to time and as per specifications mentioned in agreement of sale. independent 2. (*) Quantity surveycan be done byoffice of Engineer or can be done by an Quantity Surveyor, whose certificate of quantity calculated can be relied upon by the Engineer. Incase of independent Quantity Surveyor being appointed by Developer, the name has to be mentioned at the place marked (*) and in case quantity are being calculated by office of Engineer, the name of the person in the office of Engineer, who is responsible for the quantity calculated should be mentioned at the place marked (*). 3. (**) Balance Cost to be incurred (4)may vary from Difference between Total estimated Cost (1) and Actual Cost incurred (2) due to deviation in quantity required/escalation of cost etc. As this is an estimated cost,any deviation in quantity required for development of the Real Estate Project will result in amendment of the cost incurred/to be incurred. 4. Allcomponents of work with specifications are indicative and not exhaustive. 5. Please specify if there are anydeviations/qualifications. Example: Any deviations in input material used from specifications in agreement of sale. Table C List of Extra/Additional /Deleted Items considered in cost (Which were not part of the original Estimate of Total Cost) Sr.No. List of Extra/Additional/Deleted Items Amount (In Rs) 1 2