S.R.Infrastructure Shashank.R.Chandak M.Tech (C.M), VJTI,Mumbai B.E (Civil), VIIT, Pune Mob. : 8080364755, 8275418699 Ref. No. Date: FORM -2 ENGINEER'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account- Project wise) Date: 10/01/2025 TO, The Chandak Construction, Amravati-444601. Subject: Certificate of Cost Incurred for Development of Chandak Tower having Maha RERA Registration Number P50300051204 being developed by Chandak Construction (As on 31.12.24) Sir, ShashaukR. handok /we ....*..have undertaken assignment ofdertifying Estimated Cost for Chandak Tower having MahaRERARegistration Number P50300051204 being developed byChandak Construction. 4. We have estimated the cost of Civil, MEP and Allied works required for completion of the apartmenfs and proportionate completion of internal & external works of the project as per specifications mentioned in agreement of sale. Our estimated cost calculations are based on the pBawings / plans made available to us for the project under reference by the Developer YVonsultants. The Schedule of times and quantity required for the entire work as calculated by shhshahk R. Chandak Licensed Engineer appointed by Developer/ Engineer, the assumption of the cost of material, labour and other inputs made by developer, and the site inspection carried out by us to ascertain/confirm the above analysis given to us. 3. We estimate Total Estimated Cost of completion of the aforesaid project under reference as Rs. 1,22)90,000/- (Totalof Table Aand B) at the time of Registration. The estimated TotalCost of project i_ with reference to the Civil, MEP, and allied works required completion of the apartments and propdrtionate completion of internal & external works, as per specifications mentioned in agreement of sale and for the purpose of obtaining occupation certificate /completion certificate for the building(s)/Wing(s)/Layout/Plotted Development from the Amravati Municipal Corporation beingthe Planning Authority under whose jurisdiction the aforesaid project is being implemented. Çhandak Bungalow, Near Govt. Girls High School, Camp Road, Amravati. Maharastra. -444 602 of Estimated 4. The Estimated Cost Incurred till date is calculated at Rs.1,39,18,904/-., The amount items. Cost Incurred is calculated on the basis of input materials/services used and unit cost of these of the 5. The Balance cost of Completion of the Civil, MEP and Allied works for completion specitications apartments and proportionate completion of internal & external works, as per mentioned in agreement of sale, of the Project is estimated at Rs -16,68,904/ 6. Icertify that the Cost of the Civil, MEP and allied work for the apartments and proportionate internal & external works, as per specifications mentioned in agreement of sale, of the aforesaid Project as completed on the date of this certificate is as given in Table Aand B Below. TABLE -A Building called Chandak Tower Sr. No. Particulars Amounts Total Estimated cost of the building as on date of Registration is Rs 1,22,50,000/ 2 Cost incurred as on date of certificate Rs 1,39,18,904/ 3 Work done in Percentage (as Percentage of the estimated cost) 113.62% 4 Balance Cost tobe Incurred** (Based on Estimated Cost) Rs -16,68,904/ 5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost (Table-C) Rs TABLE -8 Internat&Eiternat Development Worcs inRe'spect of theRegistered Phase. Sr. No. Particulars Amouts 1 Total Estimated cost of the Internal and External Development Works including amenities and Rs Facilities in the layout as on date of Registration is 2 Cost incurred as on date of certificate Rs 3 Work done in Percentage (as Peree.stage of the estimated cost) % 4 Balance Cost to be ncurred (Based on Estimated Cost) Rs 5 Cost Incurred on Addiional/ Extra Items not incuded in the Estimated Cost (Table-C}: Rs Yours FaithfuiBy S S t r u c t u r e Signature of Engineer Prootetor (Licence No.ML35e...) Locat Authority itense no. Agreed and accepted by: M/s CHANDAK Signature of Promater Name: Rajgopal I ( t t avd DiesRNEehadal Date: ool- 202G Note: 1. The scope of work is to complete Registered Real Estate Project as per drawings approved from timeto time and as per specificationsmentioned in agreement of sale. 2. (*)Quantity survey can be done by office of Engineer or can be done by ar, independent Quantity Surveyor, whose certificate of quantity calculated can be relied upon by the Engineer. In case of independent Quantity Surveyor being appointed byDeveloper, the name has to be mentioned at the place marked () and in case quantity are being calculated by office of Engineer, the name of the person in the office of Engineer, who is responsible tor the quantity calculatea iould be mentionedat the place marked (*). 3. (**) Balance Cost to be incurred (4} may varyfrom'Diference between TotaB estirmated Cost:;* (1) and Açtual Cost incurred (2) due ta.deviation in quantity required/escalation of cost etc.: As this is an estimated cost, any deviatian inquantity required for devetoprment of the Reat. Estate Praject wilt result in amendment of the tost incuried/to be incurredF 4. AM componensof workwith specifications areindicative:andnot exhaustive. 5. Please specify ifthere are any deviations/qualifications. Exampie: Any deviatios in input materia used from specifications in agreement of sale. Table C List of Extra/Additional /Deleted tems considered in cost (Which were not part of the original Estimate of Total Cost) Sr.No. List of Extra/Additional/Deleted Items Amount (In Rs) 1 2