Annexure A FORM 1 [see Regulation 3| ARCHITECT'S CERTIFICATE (Tobe submitted at the time of Registration of Ongoing Project and tor withdrawal of Money from Designated Account) Date: 15/07/2024 To, Pravin SahebraoMahalle, FFS 27, Venus Plaza, Shegaon Naka Square, Amravati. 444604 Subject: Certificate orPercentage of Completion of Construction Work oflndrakshi Residency having Maha RERA Registration Numberp50300051825(Only Applicable after project Registration) being developed by Pravin SahebraoMahalle. Sir, /WeShraddha Sagane have undertaken assignment as Architect 'Licensed Surveyor of certifying Percentage of completion of Construction Work of Indrakshi Residency having Maha RERA Registration Number P50300051825(Only Applicable after project Registration. being developed by Pravin SahebraoMahalle. Based on Site Inspection, with respect to the aforesaid Real Estate Project .l certify that as on the date of this certificate, the Percentage of Work done for each of the building of the Real Estate Project under Maha RERA is as per Table Aherein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. TABLE-A Layout /Building /Wing Number(to be prepared separately for ench Layout 'Building / Wing of the Project) Sr. Tasks /Activity Percentageof Actual No. (2) Work Done () (As on dale of the Certificate) (3) Excavation 80% Basements (if any) 3 Podiums (if any) 4. Plinth 100% 5 Stilt Floor 6 Slabs of Super Structure 100% 7. Internal walls, Internal Plaster, Floorings, Doors and windows within Flats/Premises 50% 8. SanitaryFittings within the Fla/Premises 9 20% Staircases, 1lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks 60% 10. External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building Wing. 35% 11. Installation of Lifts. water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions of environment/CRZ NOC. Finishing to 25% entrance lobby;s. plinth protection, paving of areas appurtenant to Building/Wing, Compound Walland all other requirements as may be required to complete project as per specifications in agreement of Sale. Any other activities. TABLE-B Common Areas (lnternal and External Development Works) in respect of the Registered Phase / P'roject Number Common areas and Facilities Details Sr. No. Proposed Percentapge of (Yes/ No) Actual Work Done () (3) (Ason date of the (2) Certificate) (5) (4) 1 No Intemal Roads &Footpaths Bore well 100% 2. Water Supply 3 Sewerage(Chamber,lines, SepticTank, Septie Tank 80% STP). 4. Storm Water Drains No Tree planting 0 5 Landscaping &Tree Planting 6 Street Lighting No 0 No 0 7 Community Buildings 8. Treatment and disposal of sewage and No 0 sullage water. No 0 Solid Wastemanagement &Disposal 10. Water conservation / RWH 00% Rainwater harvesting No Energy management 12. No Fireprotection and fire safety requirements 13. Yes 20% Electrical meter room, sub-station, receiving station, 14. Others (Option to Add more). Yours Faithfully, Signature &Name: Shraddba Sagane (License No...) Bogon Arch. Shraddha Sagane (B. Arch.) Lic. No. CA/2016/75503 Agreed and Accepted by: PRAVINS. MAHALLE Signature of Promot®UILDERS & DEVEOPERS Name: Shop No. 27, Vinus Plaza, Date: 15/07/2024 Shegaon Naka, AMRAVATI