Annexure- B FORM-2 (See Regulation 3) ENGINEER'S CERTIFICATE (1obe submitted at the time of Registration of Ongoing Project and for withdrawal of moneY from Designated Account -Project wise) Date 07/04/2023 To, MANISHABUILDERS AND DEVELOPERS, 202, Govind Tower, Vidyut Nagar, Walgaon road, VMV, Amravati. Subject Certificate of Cost Incurred for Development of Jaee Residency-2 having MahaRERA Registration number PS0300034234 being developed by MANISHA BUILDERS AND DEVELOPERS. Sir, 1. IMiss. Ankita Haridasji Bhombe have undertaken assignment of certifying Estimated Cost for Jaee Residency-2 having MahaRERA Registration number P50300034234 (Only Applicable after project Registration) being developed by MANISHA BUILDERS AND DEVELOPERS. 2. We have estimated the cost of Civil, MEP and allied works required for completion of the apart1ments and proportionate completion of internal & external works of the project as per specifications mentioned in agreement of sale. Our Estimated cost calculations are based on the drawings/ plans made available to us for the project under reference by the Developer / Consultant. The schedule of items and quantity required for the entire work as calculated by Mr. Mahesh Vyawahare quantity Surveyor appointed by Developer/Engineer, and the assumption of the cost of material, labour and other inputs made by developer, and the site inspection carried out by us to ascertain/ confim the above analysis given to us. 3. We estimate Total Estimated Cost of completion of the aforesaid project under reference as Rs. 4,80,00,000/-, Land cost in Rs. Costruction cost in Indirect/ Other Total Project cost Rs. Expenses in Rs. Estimated in Rs. 78,21,620/ 3,89,78,380/ 12,00,000/ 4,80,00,000/ (10tal oT Table- A and B) at the time of reoistration. The estimated Total Cost of project IS with reference to the Civil. MEP and allied works apartments and proportionate completion of internalrequired for compleuon ot te and external works, as per Speciications mentioned in agreenment of sale and for the purpose of OCcupation certificate / completion certificate for the building(s) / wing(s) / obtaining7 Plotted Development from the Amravati Municipal Layout(s) Authority under whose jurisdiction the aforesaid project Corporation being the Planning is being implemented. 4. The EstimatedCost Incurred till date is calculated at Rs. 3,72,95,543/-. Land cost in Rs. Construction cost in Indirect/ Other Total Project cost Rs. Expenses in Rs. Incurred in Rs. 78,21,620/ 2,87,23,923/ 7,50,000/ 3,72,95,543/ (Total of Table- A and B) The amount of Estimated Cost basis of input material / Services used and unit cost of Incurred is calculated on the these items. 5. The Balance cost of Completion of the Civil, MEP and Allied works for completion of the apartments and proportionate completion of internal and external works, as per specifications mentioned in agreement of sale, of the project is estimated at Rs.1,07,04,457/- (Total of Table- Aand B) 6. I certify that the Cost of the Civil, MEP and Allied works for apartments and proportionate internal and external works, as completion of the per mentioned in agreement of sale, of the aforesaid Project as completed on thespecifications certificate is as given in Table A and B Below: date of this TABLE-A Building Called Jaee Residency-2 (to be prepared separately for each Building / Wing Layout/ Plotted Development of the Real Estate Project) Sr. No. Particulars Amounts Total Estimated cost of the Building/ Wing/ Layout/ (in Rs.) Plotted Development as on Mar 2022 date of Rs. 4,80,00,000/ Registration is 2 Cost incurred as on date of certificate Rs. 3,72,95,543/ 3 Work done in percentage (as Percentage of the estimated cost) 77.69% 4 Balance Cost to be incurred** (Based on Estimated Cost) Rs. 1,07,04,457/ Cost Incurred on Additional/Extra Items not included in the Estimated Cost (Table- C) Rs. TABLE-B Internal & External Development Works in Respect of the Registered P'hasC Sr. No. Particulars Amounts (in Rs.) Total Estimated cost of Internal & External 1 Development Works including amenities and Facilities in the layout as on date of Registration is Rs. 2 Cost incurred as on date of certificate Rs. 3 Work done in percentage (as Percentage of the ---% estimated cost) 4 Balance Cost to be incurred (Based on Estimated Rs. Cost) Cost Incurred on Additional/Extra Items not included Rs. in the Estimated Cost (Table- C) Yours Faithfully, ANKITA BHOMBE B.E.(Civil) Signature of Engincer. Consultng Ciil Engineer [ANKITA HARIDASJI BHOMBE] Agreed and Accepted by Signature of Promoter Name Manisha Builders and Developers tyt Date : 07/04/2023 Creie i.2o9,afq ztez, faya aaR,JAIA0-888o9 Note: 1. The scope of work is to complete Registered Real Estate Project as per drawings approved from time to time and as per specifications mentioned in agreement of sale. 2. (") Quantity survey can be done by office of Engineer or can be done by an independent Quantity Surveyor, whose certificate of quantity calculated can be relied upon by the Engineer. In case of independent quantity surveyor being appointed by Developer, the name has to be mentioned at the place marked (*) and in case quantity are being calculated by office of Engineer, the name of the person in the office of Engineer, who is responsible for the quantity calculated should be mentioned at the place marked (*). 3. (**) Balance cost to be incurred (4) may vary from Difference between Total estimated Cost (1) and Actual Cost incurred (2) due to deviation in quantity required/ escalation of cost etc. As this is an estimated cost, any deviation In quantity required for development of the Real Estate Project will result in amendment of the cost incurred/ to be incurred. 4. Allcomponents of work with specifications are indicative and not exhaustive. 5. Please specify if there are any deviations/ qualifications. Example:- Any deviation in input material used from specifications in agreement of sale. TABLE-C List of Extral Additional/Deleted Items considered in Cost (Which were not part of the original estimate of Total Cost) Sr. No. Amounts List of Extra/Additional/ Deleted Items (in Rs.) 2