Annexure A FORM 1 |see Regulation 3] ARCHITECT'S CERTIFICATE and tor withdrawal of (To be submitted at the time of Registration of Ongoing Project Money from Designated Account) Date: 7/4/2023 To, The Manisha Builders and Developers, Flat No. 201, Govind Tower., Vidyut Nagar, Amravati. 444604 Subject: Certificate or Percentage of Completion of Construction Work of Jaee Residency 2 having Maha RERA Registration Number P50300034234 (Only Applicable after project Registration) being developed by Manisha Builders and Developers Sir, I/We ShraddhaSagane have undertaken assignment as Architect 'Licensed Surveyor of certifying Percentage of completion of Construction Work of Jaee Residency 2having Maha RERARegistration Number P50300034234 ( Only Applicable after project Registration. being developed by Manisha Builders and Developers Based on Site Inspection, with respect to the aforesaidReal Estate Project .Icertify that as on the date of this certificate, the Percentage of Work done for each of the building of the Real Estate Project under Maha RERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. TABLE-A ayout /Building /Wing Nunbeto be prpand separately tor cach layvut 'uilding / Wing otthe P'roject) Sr. No, Tasks/ Activity Peventage ot Actual (2) Work Dnc (As 0ndale ot the Crtiicte) () Excavation Q0% Basements (it any) 3. Podiunns (if any) 4 Plinth l00% 5. Stilt Floor 6. Slabs of Super Structure 7. l00% Internal walls, Intenal Plaster, Floorings, Doors and windows Flats/Premises within 70% 8. Sanitary Fittings within the Flat/Premises 9. S0% Staircases, | lifts Wells and Lobbies at each Floor level Underground Water Tanks Overhead and 10. S0% External plumbing and external plaster, terraces with elevation, completion of waterproofing of the Building Wing. S0% 11. Installation of Lifts. water pumps, Fire Fighting Fittings and as per CFO NOC, Equipnment compliance to conditionsElectrical of fittings, mechanical cquipment, environmen/CRZ NOC. Finishing to entrance lobby;s. plinth protection, paving of areas appurtenant to 30% Building/Wing, Compound Wall required to complete project as perand all other requirements as may be Any other activities. specilications in agrcement of Sale. TABLE-B Common Areas (Internal and External Development Works) in respect of the Registered Phase/ Project Number Details Sr. No. Commonareas and Facilities Proposed Percentage of (Yes / No) Actual Work Done (3) (As on date of the () (2) Certificate) (5) (4) 1. No Internal Roads &Footpaths Bore well 100% 2 Water Supply 3 Sewerage(Chamber,lines, SepticTank, Septic Tank 50% STP). 4. Storm Water Drains No Tree planting 0 5 Landscaping &Tree Planting No 0 6 Street Lighting' No 0 7 Community Buildings 8 Treatment and disposal of sewage and No sullage water. 9. No Solid Waste management &Disposal 10. Water conservation RWH 00% Rain water harvesting No 11. Energy management 12 No Fire protection and fire safety requirements 13. Yes 20% Electrical meter room, sub-station, receiving station, 14. Others (Option to Add more). Yws Fthtull\. (làs (Eagaze Arch.Shraddha Sagan. (B Arch.) Lic. No. CA/2016/75503 Agrd anni A i h: Signatur ot mr Nane: Date: 0704202 e.O9,aftg etrz,