\nneire A FORM1 see Regulation 31| ARCHUTECT'SCERTIFICATE (lo be submitted at the time of Registration of Ongoing Projcet md tor withdrawal o Money Irom Designated Account) Date: 01/08/2022 To. The Manisha Builders and Developers Flat No. 201. Govind Tower. Vidyut Nagar, Amravati. 444604 Subject: Certiticate or Percentage of Completion ot C'onstruction Work of Jaee Resideney 2 having Maha RERA Registration Nunber Ps0s000.34234 ((Only Applicable alier project Registration) being developed by Manisha Builders and Developers Sir, Architect Licensed Surveyor of /WeShraddha Sagane have undertaken assignment as certilying Percentage of conmpletion of Construction Work of Jace Resideney 2 having Maha RERA Registration Number P50300034234 ( COnly Applicable alter project Registration. being a developed by Manisha Builders and Developers Based on Site Inspection, with respecl lo Layoul/ each ot the Building/Wing of the aforesaid Real Estate Project this certilicale, the Percentage ol Work done or cach of the I certify that as on the date of under Maha KERA Is as per Table A herein below. The building/Wing of the Real Estate Project is executed wilh respecl lo each ol the activily ol the entire phase percentage of the work detailed in Table B. TABLE-AA of the be prepared separately for each I.ayoul 'Building/ Wing L avout/ Building/Wing Number(to Percentage ol Aclual Project) Tasks Aetivity Sr. Work Done (2) No. (As on dale of the () Certificate) (G) Excavation 80% Excavation Basement_ (if any) Podiums (if any) 00% Plinth Stilt Floor Slabs of Super Structure 15% 6. windows within Internal walls, Internal Plaster, Floorings, Doors and 00% Flats/Premises SanitaryFittngs vwithin the Flat/Premises 00% level Overhead and Staircases, | lifts Wells and .Lobbies at each Floor 10% Underground Water Tanks 10 Exlemal plumbing and external plaster, elevation, completion of 00% terraces with waterproofing of the Building Wing 11 Installation of Lifts. water pumps, Fire Fighting Fittings and Equipmen as per CFO NOC, Electrical itings. mechanical equipment, Fnishng to compliance to conditions of environmen/CRZ NOC. entrance lobby:s. plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Any other activities. TABLE-B Common Areas (Internal and Extenal Development Works) in respect of the Registered Plhase / Project Number Sr. No. Common areas and Facilities Proposed Details Percentage of (Yes / No) Actual Work Done () (2 3) (As on dale of the Ceruficate) (5) (4) Internal Roads &Footpaths No Boarwell O0% Water Supply Sewerage(Chamber.lines,SepticTank. Septic Tank 00% STP) Storm W aler Drains No Landscaping & Tree Planting Tree plantng Street Lighting No 6. Community Buildings No and Treatment and disposal of sewage No sullage water. No Solid Waste management &&Disposall Water conservalion / RWH 00% 10. Rain water harvesting No Energy management Fire protection and fire safety Yes 12 requirenents Electrical meter room, sub-station Yes 20 receivg slation, Others (Option to Add more) 4. Yours Faithtully. Signature & Name Shraddha Sagane (icense No Agreed and Accepted by: Signature of Promoter Name: ame Date: oR,377TETit -13%E,09