Annexure- B FORM 2 [see Regulation 3] ENGINEER'S CERTIFICATE (To be submittcd at the time of registration of ongoing project and for withdrawal of Money from Designated Account-Project) TO. SAIDUTTA DEVELOPERS, Sai Heritage.Near Gajanan Maharaj Mandir, Sai Nagar, Amravati-444607. Subject: Cerificate of cost incurred for developmet of Project-SAUKRUPA having MahaRERA registration Number P50300032125 being developed by Saidutta Developers. Sir, I/We SANJAY NAGPURE & ASSOCIATES have undertaken assignement of certifying Estimated cost of PROJECT-SAIKRUPA having MahaRERA registration Number P50300032125 being developed by Saidutta Developers. 2. We have estimate the cost of Civil, MEP and allied works required for completion of the apartments mentioned and proportionate completion of internal & external works of the project as per specifications made available to in agrcement of sale. Our estimated cost calculations are based on the drawings/plans required us for the entire work as reference by developer/ Consultant. The schedule of items and quantity for the entire work as calculated by RS.4,30,19,574/- Quantity surveyor* appointed by Developer/ site Engineer, the assumptions of the cost of material, labour and other inputs made by developer, and the inspection carried out by us to ascertain/ confirm the analysis given to us. reference at 3. We estimate total Estimated Cost of completion of the aforesaid project under of project is Rs.4,30,19,574/- (Total of Table A and B) at the time of Registration. The estimated cost apartments and with reference to the Civil,MEP and Allied works required for completion of the the agreement proportionate completion of internal & external work, as per speciafications mentioned in certificate for the Building(s) of sale and fot the purpose of obtaining occupancy certificate / completion /Wing(s)YLayout/Plotted development from the being the planning Authority under whose jurisdiction the aforesaid project is implemented. ofrTable A and B). The 4. The Estimated Cost Incurred till date is calculated at Rs. 2,04,50,335/- (Total services uscd and unit amount of T:stimated Cost Incurred is calculated on the basis of input materials/ cost of these items. 5. The Balance cost of Completion of the civil, MEP and Alied works for completion of the and proportionate completion of internal & External apart1ments of Sale. of the Project is estimated at RS. works, as per specifications mentioned in agreement 2,25,69,2397- (Total of Table A and B). 6. I certify that the Cost of Civil, MEP and allied work fot the external works, as per specifications mentioned in agreement toapart1ments and proportionate internal & sale, of the aforcesaid Project as completed on date of this certificate is as given in TABLE A and B below: TABLEA WING-SAIKRUPA (TO BE PREPARED SEPARATELY FOR EACH BUILDING/WING/LAYOUT/PLOTTED DEVELOPMENT OF THE REAL ESTATE PROJECT) SR.NO. PARTICULARS AMOUNT(IN RS.) 1. Total Estimated Cost of Building/ Wing/Layout/Plotted 4,30,19,574/ Development as on Date Of Registration ls 2. Cost Incurred as on date of certificate 2,04,50,335/ 3. Work Done in percentage (as percentage ofthe estimated cost) 47% 4. Balance Cost to be Incurred+* (Based on estinmated cost) 2,25.69,239/ 5. Cost Incurred on Additional/Extra items not included in the Estimate Cost (TABLE-C) TABLE B SR.NO. PARTICULARS AMOUNTIN RS.) Total Estimated Cost of Internal and External Development Works including amenities and Facilities in the layout as on date of Registration i 2 Cost Incurred as on date of certificate Work Done in percentage (as percentage of the estimated cost) 4. Balance Cost to be Incurred** (Based on estimated cost) 5. Cost Incurred on Additional/Extra items not included in the Estimate Cost (TABLE-C) Yours Faithfully OASSO 000> 7 SignatuA t s t KLETTERS) with stamp of Engineer BE(CIV Not less than Bachelör's Degree Holder or equivalent as per section 2(u) of the Act.] L.ocal Authority license no. (if applicatble) Agreed and Accepted by: For M/s. Saidata Jevelopers Signature of Pronnoter Partnerr Name: Date: NOTE: 1. The scope of work is to complete Registered Real Estate Project as per Drawings approved from time to time as per specifications mentioned in Agreement of sale. 2. ("Quantity survey can be done by officer of Engincer or can be done by an indcpendent Quantity case of independent Surveyor, whose certificate of quantity be can be relied upon by the Engineer. In be mentioncd at the place quantity surveyor being appointed by the developer, the name has to Engineer. the namc of' the person marked () and in case quantity are being calculated by the office of calculated should be nentioned in the in the office of Engincer, who is responsible for the quantity place marked (*). Difference between Total Estimate Cost( Dand 3. (*) Balance cost to be incurred (4) may vary from of cost etc. As this is an actual cost incurred(2) due to deviation in quantity required / escalation Estate Projcct will result in of Real estimated cost, any deviation in quantity required for development amendment of the cost incurred/to be incurred. indicativw and not exlhaustive 5, Alcomponents of work with specifications re qualifications. Example: any deviation in input material 6. Please specify if there are any deviation l ISed from specifications in agreement of sale. TABLEC List of Extra ltems/Additional/Deleted Items Considered In Cost (whiclh were not part of the original Estimate ofTotal Cost) SR.NO List of Extra/Deleted Items Amount(in RS.)