CHARUL N. SARAF "CHANDRAYAN" B.E. CIVIL 16, VISHNUNAGAR, CONSULTING ENGINEER AND CONTRACTOR NEAR NEW SWASTIK NAGAR WATER TANK, OPP. AMC GARDEN, AMRAVATI -444605 PH. 07212510098, CELL -9422161910 E-MAIL : charul.saraf@ gmail.com FORM 1 ARCHITECT'S CERTIFICATE (To be submitted at the time of Registrationof Ongoing Project and for withdrawal of Money from Designated Account - Building/Wing wise) To, Date: 07/10/2023 Shri Amarnath Builders and Developers, Amravati Subject: Certificate of Percentage of Completion of Construction Work of: Chandanvadi having MahaRERA No. P50300033920 being developed by Shri Amarnath Builders And Developers as on (30/09/2023) Sir, ICharul N. Saraf have undertaken assignment as Architect/Licensed Surveyor of certifying Percentage of Completion of Construction work of Chandanvadi having MahaRERA No. P50300033920. Based on Site Inspection, with respect to of the Building of the that as on the date of this certificate, the aforesaid Real Estate Project. Icertify Percentage of Work done for each of the building of the Real Estate Project under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table-A Building Chandanvadi SrNo Tasks / Activity Percentage of Actual Work Done (1) (2) (As on date of the Certificate) 1 Excavation 100 2 Basements (if any) 100 3 Number of Podiums (if any) 100 Plinth 5 Stilt Floor 6 slabs of super structure 15 7 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises Sanitary Fittings within the Flat/Premises. Staircases, Lifts Wells and Lobbies at each Floor level 0 connecting Staircases and Lifts, Overhead and Underground Water Tanks 10 External plumbing and external plaster, elevation, 0 completion of terrace with the waterproofing of the building. 11 Installation of lifts, water pumps, Fire Fighting 0 Fittings and Equipment as per CFONOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC,Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE-B Common Areas (Iinternal and External Development Works) in respect of the Registered Phase/ Project Number S. No. Common Roads and Facilities, Amenities Proposed Percentage of Work Details (Yes/No) done 1 Internal Roads & Foothpaths No NA NA 7 Water Supply Yes 5 As per plan Y 3 Sewerage (chamber, sewage lines), Yes As per plan Storm Water Drains Storm Water Drains No NA NA 5 Landscaping & Tree Planting No NA NA 6 Street Lighting NO NA NA 7 Community Building No NA NA No NA NA Treatment and disposalof sewage and sullage water Solid Waste management & Disposal NO NA NA 10 Water conservation, Rain water Yes 0 As per plan harvesting 11 Energy management No NA NA 12 Fire protection and fire safety Yes As per plan requirements 13 Electrical meter room, sub-station, No NA NA receiving station 14 Other Yours Faithfully CHARID. A. SARAF 3.E. Civll Signature & Name (IN BLOCK LETTERS) of L. S. /Architect Consulting Engineer &Cotractor (License no.... ..) MIs.Shi Amarnath buikaers Au Uevelopers Agreed and accepted by: Partner Signature of Promoter Name: M Aput Date: so72024