FORM 1 [see Regulation 3] For Q 2 of 2024 – 30.06.2024 ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) Date: 14/10/2024 To, Raj Associates Subject: Certificate of Percentage of Completion of Construction Work of Raj Township having MahaRERA Registration Number P50300022183 being developed by Raj Associates. Sir, I/ We Khurshid Munshi have undertaken assignment as Architect/Licensed Surveyor of certifying Percentage of Completion of Construction Work of Raj Township having MahaRERA Registration Number P50300022183 being developed by Raj Associates. Based on Site Inspection, with respect to Layout / each of the Building/Wing of the aforesaid Real Estate Project, I certify that as on date of this certificate the Percentage of Work done for each of the building/Wing of the Real Estate Project under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. TABLE - A Layout / Building/ Wing Number _____ (to be prepared separately for each Layout / Building / Wing of the Project) Sr Task / Activity Percentage of No. (2) Actual Work (1) Done (As on date of the Certificate) (3) 1. Excavation 100% 2. Basements (if any) 100% 3. Podiums (if any) 100% 4. Plinth 100% 5. Stilt Floor 100% 6. Slabs of Super Structure 100% 7. Internal walls, Internal Plaster, Floorings, Doors and 100% Windows within Flats/Premises 8. Sanitary Fittings within the Flat/Premises 100% 9. Staircases, Lifts Wells and Lobbies at each Floor level, 80% Overhead and Underground Water Tanks 10. External plumbing and external plaster, elevation, 50% completion of terraces with waterproofing of the Building/Wing. 11. Installation of lifts, water pumps, Fire Fighting 0% Fittings And Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment/CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building / Wing, Compound Wall and all other requirements as maybe required to complete project as per specifications in agreement of Sale. Any other activities. Table B Common Areas (Internal and External Development Works) in respect to the Registered Phase / Project Number Sr. Common areas Proposed Percentage Details No and Facilities. (Yes/No) of (5) (1) Work done (2) (3) (As on date of the 1. Internal Roads& Yes 100% As Applicable Footpaths Certificate) (4) 2. Water Supply Yes 100% As Applicable 3. Sewerage (chamber, lines, Yes 100% As Applicable Septic Tank, STP) 4. Storm Water Drains Yes 100% As Applicable 5. Landscaping & Tree Yes 100% As Applicable Planting 6. Street Lighting Yes 100% As Applicable 7. Community Buildings Yes 100% As Applicable 8. Treatment and disposal of Yes 100% As Applicable sewage and sullage water 9. Solid Waste management Yes 100% As Applicable & Disposal 10. Water conservation, Rain Yes 100% As Applicable water harvesting 11. Energy management Yes 100% As Applicable 12. Fire protection Yes 100% As Applicable And fire safety requirements 13. Electrical meter room, Yes 100% As Applicable sub-station, receiving station