*E}ESIGN PLUS*' grorrP AN ARCHITECTURAL CONSULTENCY SERVICES 02 ,Ritesh plaza , Swastika ilagar, Hawate Square , Badnera Road , Arnravati - 444605 Dztez fi7/AU202l To, AMBER BUILDERS & DEVELOPERS, THROUGH PARTNIERS SMT. SEEMA SANJAY RATHI & SHRI. PRAKASH S. KELA. AMRAVATI. Subject: Certificate of Percentage of Completion of Construction Work of AMBER PARK having Maha RERA Registration Number P50300024763 being developed by AMBER BUILDERS & DEVELOPERS, THROUGH PARTNERS SMT. SEEMA SANJAY RATHI & SHRI. PRAKASH S. KELA, AMRAVATI. Sir, I Ar. RAHUL FARKADE have undertaken assignment as Architect / Licensed Surveyor of certiffing Percentage of Completion of Construction Work of annnpn PARI( Having Maha RERA Registration Number P50300024763 being developed by AMBER BUILDERS & DEVELOPERS, THROUGH PARTNERS SMT. SEEMA SANJAY RATTII & SHRI. PRAKASH S. KELA, AMRAVATI. Based on Site inspection, with respect to Layout / each of the Building /Wing of the afbresaid Real Estate Pro-iect, I certifr that as on the date 31.12.2020 of this cefiificate, the Percentage of Work done for each of the building Aving of the Real Estate Project under Maha RERA is as per Table A here in belorv. The percentage of the 'work executed r*-ith respect to each of the activity of the entire phase is detailed in Table B. RAHUL FA B.Arch. cA / 200 Ud-");.' TABLE _ A Layout/Building/WingNumber (AIVIBER PARI(" BUILDING-2 WING C & D (to be prepared separately for each LayouUBuilding/Wing of the project) Sr. No. Task / Activity Percentage of actual work done (1) at (3) I Excavation 8Ao/a 2 Basements (if any) N.A. 3. Podiums (if any) N.A, 4 Plinth 5Yo 5 Stilt floor 00% 6 Slabs of Super Structure a0% 7 Internal Walls, Internal Plaster, Flooring, Doors and AUYa Windows within Flats/ Premises 8. Sanitary Fittings within the Flats/Premises. a0% 9 Staircases, Lifts wells and Lobbies at each Floor level, 0a% Overhead and Underground Water Tanks. 10. The external plumbing and external plaster, elevation, $AYo completion of terraces rx-ith WaGrproofing of the Building/Wing. 11. Installation of lifts. water pumps, Fire Fighting Fittings and 00Ya equipment as per CFO NOC. Electrical fittings. mechanical equipment, Compliance to conditions of environment/CRz NOC, Finishing to entrance lobby/s, plinth protection, paying of areas appurtenant to Building/Wing, compound wall and all other requirements as may be required to complete the project as per specifications in agreement of Sale. Any other activities. TABLE _B Common Areas (lnternal and External Development Works) in respect of the Registered Phase,{Project Number Sr. Common Areas and Facilitieq Proposed Percentage Details No. (YesA{o) of actual work done (1) (2) (3) (4) (s) I lntemal Roads & Footpaths YES 00% 2. Water Supply YES 0ao J Sewerage ( chamber, lines , YES 000h septic TanK STP) 4 Strom Water Drains YES A0o/o 5 Landscaping & Tree Planting YES 00% RAHUL FA EE B.Arch. cA / 200v 6. Street Lighting YES Atr/o 7 Community Buildings YES AAYy 8. Treatment and disposal of YES 00% sewage and sullage water. 9 Solid Waste management & YES 00% Disposal 10. Water conservation i YES 00% Rain water harvesting. lt Energy management YES $AYo 12. Fire protection and fire safety YES aao requirements. 13. Electrical meter room. sub- YES AUYo station. receiving station. 14. Others (option to Add more). N.A. N.A. Yours Faithfully, RAHUL FA DE B.Arch. eA / 200 AT. RAIIUL FARKADE (License No. CA/2007 I 40264) Architect's Signature & Name Agreed and Accepted b1,, AMBER BUILDERS & DEVELOPERS Promoter's Signature & Naf6f Ambar Builden & Developers 1) SMT. SEEMA SANJAY RATIII 4Y- Partner For Ambar Btrilders 8, &+veloPers -s. 2) SrrRr. PRAKASH S. KELA Date: 07.01.2021