Annexure A FORM 1 |see Regulation 31| ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and tor withdrawal of Money from Designated Account) Date: 7/01/2023 To, The P.S. Associates, FFS-27, Venus Plaza, Shegaon Naka square, Amravati. 444603 Subject: Certificate or Percentage of Completion of Construction Work of Gajanan Plaza having Maha RERA Registration Number Ps0300028882 (Only Applicable after project Registration) being developed by P.S. Associates Sir, I/WeShraddha Sagane have undertaken assignment as Architect Licensed Surveyor of certifying Percentage of completion of Construction Work of Gajanan Plaza_ having Maha RERA Registration Number P50300028882 ( Only Applicable after project Registration. being developed by P.S. Associates Based on Site Inspection, with respect to Layout / each of the Building/Wing of the aforesaid Real Estate Project I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project under Maha RERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. TABLE-A Layout/ Building/ Wing Number(to be prepared separately for each Layout 'Building/ Wing ofthe Project) Sr. Tasks/ Activity Percentage of Actual No. Work Done (2) (1) (As on dale of the Certificate) (3) . Excavation Excavation 100% 2. Basements (if any) 3. Podiums (if any) Plinth 100% 4. 5. Stilt Floor Slabs of Super Structure 6. 100% 7. Internal walls, Internal Plaster, Floorings, Doors and windows within 100% Flats/Premises 8. SanitaryFittings within the Flat/Premises 100% Staircases, I lifts Wells and ,Lobbies at each Floor level Overhead and Underground Water Tanks 100% 10. External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building Wing. 100% 11. Installation of Lifts. water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions of environment/CRZ NOC. Finishing to 100% entrance lobby;s. plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Anyother activities. TABLE-B Common Areas (Internal and External Development Works) in respect Number of the Registered Phase/ Project Sr. No. Common areas and Facilities Proposed Details Percentage of (Yes/No) Actual Work Done (1) (2) (3) (As on date of the Certificate) (5) (4) 1. Internal Roads &Footpaths No . Water Supply Boarwell 100% Sewerage(Chamber,lines, SepticTank, Septic Tank STP). 100% 4. Storm Water Drains No 5. Landscaping &Tree Planting Tree planting 100% 6. Street Lighting No 7. Community Buildings No 8. Treatment and disposal of sewage and sullage water. No 9. No Solid Waste management &Disposal 10. Water conservation/ RWH 100% Rain water harvesting 11. Energy management No 12. Fire protection and fire Yes safety requirements Yes 100% 13. Electrical meter rom, sub-station, receiving station, 14. Others (Option to Add more). Yours Faithfully, Signature & Name :Shraddha Sagane (License No....s ngane Arch. Shraddha Sagane E. Arch.) i c . No. C A ! 7 0 1 5 / 7 5 5 0 3 Agreed and Accepted by: Signature of Promoter Name: Name Date: P.S.ASSOCIATESS FF27, Vinus Plaza, Shegaon Wako, Amravati