Annexure- B FORM-2 (See Regulation 3) ENGINEER'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of money from Designated Account - Project wise) Date - 09/10/2024 To. The Mauli Associates, FFS- 27, Venus Plaza, Shegaon Naka square, Amravati-444603 Subject: Certificate of Cost Incurred for Development of Mauli Complex having Maha RERA Registration Number Ps0300028628 being developed by Mauli Associates for the periodending with September 2024. Sir. 1. IMiss. Mayuri Devidas Asole have undertaken assignment of certifying Estimated Cost for Mauli Complex having Maha RERA Registration Number PS0300028628 being developed by Mauli Associates. 2. We have estimated the cost of Civil, MEP andallied works required for completion of the apartments and proportionate completion of intermal & extenal works of the project as per specifications mentioned in agreement of sale. Our Estimated cost calculations are based on the drawings/ plans made available tous for the project under reference by the Developer /Consultant. The schedule of items and quantity required for the entire work as calculated by Mr. Mahesh Vyawahare quantity Surveyor appointed by Developer/Engineer, and the assumption of the cost of material, labour and other inputs made by developer, and the site inspection carried out by us to ascertain/ confirm the above analysis given to us. 3. We estimate Total Estimated Cost of completion of the aforesaid project under reference as Rs. 13,05,05,000/ Land cost in Rs. Construction cost in Indirec/ Other Total Project cost Rs. Expenses in Rs. Estimated in Rs. 1,95,61,784/ 10,81,40.020/ 28.03.196/ 13,05,05,000/ (Total of Table- A and B) at the time of registration. The estimated Total Cost of project is with reference to the Civil, MEP and allied works required for completion of the apartments and proportionate completion of internal and external works, as per specifications mentioned in agreement of sale and for the purpose of obtaining occupation certificate /l completion certificale for the building(s) /wing(s) /Layout(s) / Ploted Developmentfrom the Amravati Municipal Corporation being the Planning Authority under whose jurisdiction the aforesaid project is being implemented. 4. The Estimated Cost Incurred tilldate is calculated at Rs. 8,94,24,996/-. Land cost in Rs. Construction cost in Indirect/ Other Total Project cost Rs. Expenses in Rs. Incurred in Rs. 1.95.61.784/ 6.77,64.212/ 20,99.000/ 8,94,24.996/ (Total of Table- A and B) The amount of Estimated Cost Incurred is calculated on the basis of input material /Services used and unit cost of these items. 5. The Balance cost of Completion of the Civil, MEP and Allied works for completion of the apartments and proportionate completion of internal and external works, as per specifications mentioned in agreement of sale, of the project is estimated at Rs.4,14,80,004/- (Total of Table- A and B) 6. I certify that the Cost of the Civil, MEP and Allied works for completion of the apartments and proportionate internal and external works, as per specifications mentioned in agreement of sale, of the aforesaid Project as completed on the date of this certificate is as given in Table A and B Below: TABLE-A Building Called Mauli Complex (to be prepared separately for cach Building/ Wing/ Layout/ Plotted Development ofthe Real Estate Project) Sr. No. Particulars Amounts (in Rs.) Total Estimated cost of the Building as on Mar 2021 1 Rs. 13,05,05.000/ date of Registration is Cost incurred as on date of certificate Rs. 8,94,24,996/ 3 Work done in percentage (as Percentage of the 68.52% estimated cost) Balance Cost to be incurred** (Based on Estimated 4 Cost) Rs. 4,10,80,004/ Cost Incurred on Additional/Extra Items not included Rs. Associates 09/10/2024 Date: Name- Mauli Signatureof Agreed No.Sr. 4 2 1 2. 1.Note: and upon independent (*) approved The CostCost) in Balance Cost estimated to Estimated Facilities cost)Work Cost Development Works Total Internal in Promoter Accepted the the Quantity scope by Incurred incurred Estimated Estimated done the in & from External Quantity of by the Engineer. survey timework on in as Cost Additional/Extra percentage layout on be Cost to date cost (Table- incurred (Based Development Particulars (Table- Surveyor,In can time is to as of case on amenities includingInternalof& complete be and certificate C) (as date done C) of whose as -2?ia20, Items Percentage of Works TABLE -B independent per Consulting MAYURI ASOLE by Registered Registration specifications certificate on office not in included Estimated Respect External Civil of quantity of Real isand of B.E. 2le the Engineer Engineer of quantitymentionedEstate (CiYAYURI the surveyor Engineer. Signatureof Registered calculated orProject Consulting Faithfully, Yours can in being agreement Rs. Rs. DEVIDAS Rs. Rs.-- - Amounts Rs.)(in be as -- ---% Phase -- appointed candone per Civil B.E.(Civil) bedrawings of EngineerASOLE relied bysale. by an No.Sr. 2 5. 4. 3. inputPlease Al incurred/ for place are (*).Developer, Engineer, estimated (**) marked escalation componentsdevelopment being material Balance List (Which List specify to Cost calculated who of be of the of cost Extra/ Extra/Additional/ used if incurred. (1) cost is name were there work of ofetc. and responsible from byhas Additional/ not are the As to Actual be part specifications with Real this office to any incurred be of TABLE-C specifications Estate Cost is fo r mentioned of Deleted ltems the Deleted deviations/ an th e original estimatedincurred (4) Engincer, Project quantity in may Items agreement qualifications. at estimate are (2) the the considered indicative will cost, vary calculated place due name of of result any to from marked Total sale. deviation deviation of in Example:- and in Difference should th e Cost) Cost amendment not person () exhaustive. In in be and Amounts quantity quantity Rs.(i)n Any mentioned in in between deviation of the case required/ th required oflice quantity cost Total at in th e of