Ar. Bhagyashree Bhamare 09, Ratnprabha Residency, Tidke Colony, Near Mumbai Naka, Nashik- 422002 Form 1 (See Regulation 3) ARCHITECT’S CERTIFICATE (To be submitted at the time of Registration of Ongoing project and for Withdrawal of Money from Designated Account) Date: 24.10.2024 To The Partners, M/s. Shri Balaji Infra Plot No.3, Pushpanjali Niwas, Water Filter Road, Waman Nagar, Opposite Swami Tower, Khamgaon- 444303. Subject: Certificate of percentage of completion of construction work of “Rama Elite” having MahaRERA Registration Number: (To Be Applied) being developed by M/s. Shri Balaji Infra. Sir, I Bhagyashree Rajendra Bhamare have undertaken assignment as Architect/Licensed Surveyor of certifying percentage of Completion of Construction work of the “Rama Elite” having MahaRERA Registration Number: (To Be Applied) being developed by M/s. Shri Balaji Infra. Based on site Inspection, with respect to layout/each of the building/wing of the aforesaid Real Estate project. I certify that as on the date of this certificate, the percentage of work done for each of the building/wing of the Real Estate project under MahaRERA is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in table B. Table A Layout/Building/Wing No “Rama Elite” (To be prepared separately for each layout/building/wing of the project) Sr. No. Task/Activity Percentage of actual work done (As on 30.09.2024) (1) (2) (3) 1. Excavation 100% 2. Basements (if any) 10% 3. Podiums (If any) NA 4. Plinth 0% 5. Stilt Floor 0% 6. Slabs of Super Structure 0% 7. Internal Walls, Internal Plaster, Floorings, Doors and Windows 0% Within Flats /Premises 8. Sanitary Fittings Within the Flat/Premises 0% 9. Staircases, Lifts Wells and Lobbies at each Floor level overhead and 0% Underground Water Tanks 10. External plumbing and external Plaster, Elevation, completion of 0% terraces with waterproofing of the building/wing. 11. Installation of Lifts, Water pumps, Fire Fighting Fittings and 0% Equipment as per CFO NOC, Electrical Fittings, Mechanical Equipment, Compliance to conditions of environment / CRZ NOC, finishing to entrance Lobby/s, plinth Protection, paving of areas appurtenant to Building/Wing, Compound wall and all other requirements as may be required to complete the project as per specifications in agreement of sale. Any other activities. Table B Common Areas (Internal & External Development Works) in respect of the registered phase /project number Sr. No. Common areas and Proposed Percentage of Details Facilities, Amenities (Yes/No) Actual Work Done (As on 30.09.2024) ) (1) (2) (3) (4) (5) 1. Internal Roads and No 0% NA Footpaths 2. Water Supply Yes 0% NA 3. Sewerage (chamber, Lines, Yes 0% No STP Septic Tank, STP) 4. Storm Water Drains No 0% NA 5. Landscaping &Tree Planting No 0% NA 6. Street Lighting No 0% NA 7. Community Buildings No 0% NA 8. Treatment and Disposal of No 0% NA Sewage and Sullage water 9. Solid Waste Management & No 0% NA Disposal 10. Water Conservation/Rain Yes 0% Only Rain Water Water harvesting Harvesting 11. Energy Management No 0% NA 12. Fire Protection and Fire No 0% NA Safety Requirements 13. Electrical meter room, Sub- Yes 0% Only Electric Meter Box Station, Receiving station 14. Aggregate area of recreational Yes 0% Terrace Garden Open Space 15. Others (Option to Add more) No 0% NA 16. Terrace Garden Yes 0% NA 17. Terrace Green Gym Yes 0% NA Yours Faithfully AR. BHAGYASHREE RAJENDRA BHAMARE License No. – CA/2019/105017 Agreed and accepted by: For, M/s. Shri Balaji Infra Signature of Promoter Name: Pritesh Manoj Modi Designation: Partner Date: 24.10.2024