ENGINEERS ARCH ITECTS INIE RIOR DES IGN E RS 5,8-WING ( Upper Gr.Floor ), VIMACO TOWER, BUS STAND ROAD, AMRAVATI - 444602 ( M,S.) R.V. B e I a n k a r & C o, r"r.,o;zr,zss274o (o) tMe4221 sss35 e-mail : rbelankar@gmail.com FORM-2 I See Regulation 3] ENG IN EER,S CERTIFICATE (To be submitted at the time of registration of ongoing Project and for withdrawal of Money from Designated Account) Date : 21-01-2023 To Name :- ADIL CONSTRUCilON Address of Promoter:-Bhagyashree Colony, Camp, Amravati-444602' subject : certificate of Percentage of completion of construction work of 1 No. of Building .N.No/CTSNo./Survey no' Gut No' 19 Plot no'18 Final demarcated by its boundaries (latitude and longitude of the end points) Gut no:- 3, to the North plot no.4. to the south plot no.2 to the East 30 m road of the west service lane of Division Amravati village Amravati Taluka Amravati District Amravati PIN 4/14602 Admeasuring 658.58 sq.mts. area being developed by M/s Adil constructions Partner Aneeque Ahmed Khan Ref : MahaRERA registration Number :- P-50300018496 Sir, I Rajendra V. Belankar have undertaken assignment as Architect / Licensed of the surveyor of certifying Percentage of completion of construction work above Building of the Project, situated on the plot bearing Gut. No./Surveyno No:-19 Nazul Plot no.18, Layout plot 3 of Division Amravati' village Amravati Taluka Amravati. District Amravati. PIN 4rM5O2 Admeasuring 658'58 sq'mts' area being develoPed bY :- M/S Following technical professionals are appointed by Owner/ Promoter Adil Constructions Partner Aneeque Ahmed Khan' 1 i) M/s Rajendra V.Belankar as L.S. /Architect / engineer ii) Shri Pankaj Subhashrao Deshmukh Structure Consultant iii) Shri.Ashish Wankhade as MEp Consultant iv) Shri Rajendra V Belankar euantity Surveyor 2' we have estimated the cost of the compretion to obtain occupation completion certificate, of the civir, MEp and Ailied works, of the / Buirding(s) of the project' our estimated cost carcurations are based on it. Drawings/plans made avairabre to us for the project under reference by the Developer and consurtants and the schedure of items and quarity roi tne entire work as calculated by _--__ quality Surveyor* appointed by Developer/Engineer, and the assumption of the cost of materiar, rabour and other inputs made by developer, and the site inspection carried out by us. 3. we estimate Totar Estimated cost of compretion of the proposed part of building of the aforesaid project under reference as Rs 3,50,75,G45/_ (Total of Table A and B)' The estimated Totar cost of project is with reference to the civil, MEP and alried works required to be compreted for the purpose of obtaining occupation certificate / compretion certificate for the buiiding(s) from the Town planning being the planning Authority under whise jurisdiction the aforesaid project is being implemented. 4. The Estimated Cost lncurred till date is calculated at 2,98,14,29g/_ (Total of Table A and B)-. The amount of Estimated cost lncurred is calculated on the base ofamount ofTotal Estimated Cost. 5. The Balance cost of compretion of the civir, MEp and Ailied works of the Building(s) of the subject project to obtain occupation certificate / Completion Certificate from Town planning (planning Authority) i; estimated at Rs 52,G1,346/-(Total ofTable A and B). 6. I certify that the cost of the civir, MEp and allied work for the aforesaid Project as completed on the date of this certificate is as given in Table A and B below: TABLE A Building / Wing bearing Number or called (to be prepared separately for each Building / Wing of the Real Estate project) Sr. Particulars Amounts I No. 1 Total Estimated cost of the buildin g as on 19-06-18 3,5O,75,6451- 2 Cost incurred as on superstructure with brickwork & 2,98,14,298/- art finishing (based on the Estimated cost 3 Work done in Percentage 8s% (as Percentage ofthe estimated cost ) 4 Balance Cost to be lncurred 52,61.,346/- (Based on Estimated Cost 5 Cost lncurred on Additional /Extra Items not 0.00 included in the Estimated Cost (Ann exure A) TABLE B (to be prepared forthe entire registered phase ofthe Real Estate project) Sr. Particulars Amounts No. 7 Total Estimated cost of the lnternal and External 3,5O,75,6451- Development Works including amenities and Facilities in the la yout 2 Cost incurred 2,98,14,298/- (based on the Estimated cost ) 3 Work done in Percentage 85% as Percentage of the estimated cost 4 Balance Cost to be lncurred 52,61.,3461- (Based on Estimated Cost 5 Cost lncurred on Additional / Extra ltems not 0.00 included in the Estimated Cost (Annexure A (Rajendra V Belankar) Civil Engineer L. No: DDMCA/R/ 2022/ APL/ 00676 o v * * P.