SANDIPR TOSHNIWAL Municipal LIC/CivilEngineer Municipal LIC No. LE/00001/2014-15 Annexure-B FORM-2 [SEE REGULATION3] ENGINEER'S CERTIFICATE Designated AcCount- Project Wise) (To Be Submitted at the time of Registration of Ongoing Project and for withdrawal of Money from (Form Issued for the cost incurred till 30.06.2023 (Q -1 - FY, 2023-24) Date:16/10/2023 To, Mangalam Infra, Project - Mangalam Park Shop No. 27, Mansingka Building, Jamner Road, Pachora Tal: PachoraDist: Jalgaon 424 201 Registration Number Subject: Certificate of Cost Incurred for Development of "Mangalam Park" having MahaRERA P49900025679 being developed by "Mangalam Infra" Sir, Estimated Cost for |I SandipRatanlalToshniwalhaving PAN : AAGPT7729K have undertaken assignment of certifying "MANGALAM PARK" having MahaRERA Registration Number- P49900025679being developed by Mangalam Infra" 1. We have estimated the cost of Civil, MEP and allied works required for completion of the apartments and proportionate completion of internal & external works of the project as per specifications mentioned /n agreement of sale. Our estimated cost calculations are based on the drawings/ plans made available to us for the proiectunder reference by the Developer /Consultants. The Schedule of items and quantity required for the entire work as calculated by Quantity Surveyor* appointed by Developer/Engineer, the assumption of the cost of material. Labor and other inputs made by developer and the site inspection carried out by us to ascertain / confirm the above analysis given to us. 2. We estimate Total Estimated Cost of completion of the aforesaid project under reference at Rs.29,67,33,600/- (Total A And B) at the time of Registration. The estimated Total cost of project is with: reference to the Civil , MEP and Allied works required for completion of the apartments and proportionaje completion of internal & external works as per specifications mentioned in agreement of sale and for the purpose of obtaining occupation certificate/completion certificatefor the building(s) Wing(s) / Layout plotted Development from the "Municipal Corporation"Pachora,424 201 being the Planning Authority Under Whose Jurisdiction the aforesaid project Is being implemented. office: 61, GANESH COLONY, PACHORA, DIST :JALGAON 424 201 Mob: 88882-26226 SANDIP RTOSHNIWAL Municipal LICICivil Engineer Municipal LIC No. LE/O0001/2014-4E 3. Estimated Cost Incurred till 30.06.2023 Is Calculated at Rs.11,50,32,012/- (Total of Table AAnd Bi t amount of Estimated Cost Incurred is calculated on the basis input materials / services used and unit cot these items. 4. The Balance Cost of Completion of the Civil MEP and Allied Works for completion of the apariments a proportionate completion of internal &external works as per specifications mentioned in agreemunt of uie of theproject is estimated at Rs. 18,17,01,588/- (Total of Table Aand B) 5. Icertify that the Cost of the Civil MEP and allied Work for the apartments and proportionate intermal external works, as per specifications mentioned in agreement of sale of the aforesaid Project as Complete S on the date of this certificate is as given in Table A and B below. 1 TABLE A Building/Wing / Layout / Plotted Development bearing Number Project:Mangalam Park" Located at :CTS No.107/2 B,Pungaon Road, PachoraDist: Jalgaon 424 201 (to be prepared separately for each Building /Wing/ Layout/ Plotted Development of the Real 2 Estate Projectj Sr.No Particulars Amount (In Rs.) 1 Total Estimated Cost of the Building /Wing Layout /Plotted Development as on date of Registration is 29,67,33,600/ 2 Cost incurred as on date of certificate 11,50,32,012/ - 5 3 Work done in Percentage 38.77% (as Percentage of the estimated cost) Balance Cost to be Incurred** (Based on Estimated Cost) Yo 18,17,01,588/ Sig Sar 5 Cost Incurred on Additional /Extra Items Loc not included in the Estimated Cost (Table-C) Agr Nar Aut Dat Office: 61, GANESH COLONY, PACHORA, DIST : JALGAON 424 201 Mob: 88882-26226 SANDIPR TOSHNIWAL er Municipal LIC/Civil Engineer 15 Municipal LIC No. LE/00001/2014-15 The S and salel TABLE B (Internal &external Development Works in Respect of the Registered Phase) nal -pleted Sr.No Particulars Amount (In Rs.) 1 Total Estimated Cost Of the Internal and External Development Works NA Including amenities and Facilities In the layout as on date of Registration is PungaoƱ 2 Cost Incurred as on date of certificate NA 3 Work done in percentage (as Percentage of the estimated Cost) NA Balance Cost to Be Incurred** (Based on Estimated Cost) NA Cost incurred on Additional/ Extra Items not included in the NA Estimated Cost (Table- c) Your Faithfully, SANDI neer Reg.No. Signature &Name LE/P0001 2014-15 Lic SandipkatanlalToshni horaMun Local Authority license ro Mt S00001/2014-15 Agreed and fccepted by: Pachora Name: Rtesh Suresh Lalwani Authorised Partner of "Mangalam Infra Date: 16/10/2023 Office: 61, GANESH COLONY, PACHORA, DIST:JALGAON 424 201 Mob: 88882-26226 SANDIPR TOSHNIWAL Municipal LIC/Civil Engineer Municipal LIC No. LE/00001/2014-15 Note 1 The scope of work is to Registered Real Estate Project as per drawings approved form time to time ad as per specifications mentioned in agreement of sale. e: 16 2 Quantity survey can be done by office of Engineer or can be done by an independent Quantityangala Surveyor, whose certificate of quantify calculated can be relied upon by the Engineer. In case of Ject independent quantity surveyor being appointed by developer the name has to be mentioned at the place op Ne marked (*) and in case quantity are being calculated by office of Engineer, the name of the person in the mner office of Enginer, who is responsible for the quantity calculated should be mentioned at the plage al :Pa marked (*) ubjec 3 (**) Balance Cost to be incurred (4) may vary from Difference between Total estimated Total estimated 49900 cost (1) and Actual Cost incurred (2) due to deviation in quantity required/escalation of cost ete. AS this is an estimated cost any deviation in quantity required for development of the Real Estate Project 5it, willresult in amendment of the cost incurred/ to be incurred. il Sanc 4 All components of work with specifications are indicative and not exhaustive. MAN 5 Please specify if there are any deiations / qualifications Example: Any deviations in input material 1 used from specifications in agreement of sale. Table -C List of Extra/Additional /Deleted Items considered in cost (which were not part of the original Estimate of Total Cost) 2 Sr. No List of Extra / Additional /Deleted Items Amotnt (inRs) NIL NL 2 NIL NIL Ofice: 61, GANESH COLONY,PACHORA, DIST :JALGAON 424 201 Mob: 88882-26226