Amit Construction 8c Engineers Amit M. Lakhe (Civil Engineer) ACE. mob.8830427078/ 7798552498 E-mail: aceengineers22@gmailcom Date • 06/01 /2020 FORM-2 [see Regulation 3] ENGINEER'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account- Project wise) To, FOR - MS. V4 INFRA, MR. KISHOR V. BHOOT, WARDHA. Subject: Certificate of Percentage of Completion of Construction Work of Single (1) No. of Building of the " Tulip Tower " Project [Maha RERA Registration Number] situated on the Plot bearing ,Survey No. 44/ Final Plot no. 15 & 16a demarcated by its boundaries (latitude and longitude of the end points) Plot No. 16b at East, Plot No.14 At West, Plot No. 25 & 26 at North, 9.14 mts. Layout Road at South (Old House), of Village - Palakwadi , Taluka - Wardha, District - Wardha, PIN - 442001 , admeasuring - 401.37 Sq.Mtrs. area being developed by V4 INFRA, WARDHA. Ref: MahaRERA Registration Number P50400013538 Sir, I/ We Amit Lakhe have undertaken assignment of certifying Estimated Cost for the Subject Real Estate Project proposed to be registered under MahaRERA, being Tulip Tower Building situated on the plot bearing, Survey No. 44/ Final Plot no. 15 & of Village - Palakwadi, Taluka - Wardha, District - Wardha, PIN - 442001, admeasuring - 401.37 Sq.Mtrs. area being developed by V4 INFRA, WARDHA. 1. Following technical professionals are appointed by Owner / Promoter: - (i) Shri Swapnil Khedikar as Architect; (ii) Shri Dinesh Lakde as Structural Consultant (iii) Shri Nil as MEP Consultant (iv) Shri Amit Lakhe as Quantity Surveyor 2, We have estimated the cost of the completion to obtain Occupation Certificate/ Completion Certificate, of the Civil, MEP and Allied works, of the Building(s) of the project. Our estimated cost calculations are based on the Drawings/plans made available to us for the project under reference by the Developer and Consultants and the Schedule of items and quantity for the entire work as calculated by Amit Lakhe quantity Surveyor* appointed by Developer/Engineer, and the assumption of the cost of material, labour and other inputs made by developer, and the site inspection carried out by us. AMIT BUILDING Eigg. & Contractor Mob.- 7798552498 Add. Satoda, Post Nalwadi, Wardha from the Town Planner, Municipal Corporation, Wardha being the Planning Authority under whose jurisdiction the aforesaid project is being implemented. 4. The Estimated Cost Incurred till date is calculated at Rs.1,46,94,443 (Total of Table A and B) The amount of Estimated Cost Incurred is calculated on the base of amount of Total Estimated Cost. 5. The Balance cost of Completion of the Civil, MEP and Allied works of the Building(s) of the subject project to obtain Occupation Certificate / Completion Certificate from Town Planner, Municipal Corporation, Wardha (planning Authority) is estimated at NIL (Total of Table A and B). 6. I certify that the Cost of the Civil, MEP and allied work for the aforesaid Project as completed on the date of this certificate is as given in Table A and B below: Table A Building /Wing – Tulip Tower (to be prepared separately for each Building /Wing of the Project) Sr.No. Particulars Amounts 1 Total Estimated cost of the building/wing Rs. 1,46,94,443 /- as on date of Registration is 2 Cost incurred as on 31/10/2019 1,46,94,443 (based on the Estimated cost) 3 Work done in Percentage 100.00% (as Percentage of the estimated cost) 4 Balance Cost to be Incurred NIL (Based on Estimated Cost) 5 Cost Incurred on Additional /Extra Items NIL as on _____________not included in the Estimated Cost (Annexure A) Table B (to be prepared for the entire registered phase of the Real Estate Project) Sr.No. Particulars Amounts 1 Total Estimated cost of the Internal and External Rs. 1,46,94,443 /- Development Works including amenities and Facilities in the layout as on date of Registration is 2 Cost incurred as on 31/10/2019 1,46,94,443 (based on the Estimated cost) 3 Work done in Percentage 100.00% (as Percentage of the estimated cost) 4 Balance Cost to be Incurred NIL (Based on Estimated Cost) 5 Cost Incurred on Additional /Extra Items NIL as on _____________not included in the Estimated Cost (Annexure A) Yours Faithfully Date: 06/01/2020 Signature of Engineer