AR. PRIYANKA CHENDULKAR B. ARCH RukhminiNagar,Amravati Mob:9545482911 FORM 1 ARCHITECT'S CERTIFICATE To. Date: 31/09/2023 The GAYATRI BUILDERS AND DEVELOPERS (NITIN JUGALKISHOR CHENDULKAR), Subject: Certificate of Cost Incurred for Development of PARIKRAMA GREENS having MahaRERA Registration Number P50300011577 (Only applicable after Project Registration)being Developed by Gayatri Builders and Developers. Sir. 1/We PRIYANKA CHENDULKAR have undertaken assignment as Architect/ Licensed Surveyor of Certifying Percentage of Completion of Construction Work of Parikrama Greens having MahaRERA Registration Number P50300011577 (Only applicable after Project Registration) being Developed by Gayatri and Developers. Builders Based on the Site Inspection, with respect to the Layout /each Building/Wing of the aforesaid Real Estate Project, I certify that as on date of this Certificate, the Percentage of Work Done for each of the Building/Wing of the Real Estate Project under MahaRERA is as per Table-A herein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Table-B. Table A Building /Wing Number 1 (ABC Wing) in Parikrama Greens (to be prepared separately for each Layout/Building/Wing of Project) Percentage of Actual Work Sr. No. Tasks / Activity Done (As on date of Certifcate) 1 Excavation 100% 2 Basements (if any) 3 Podiums(if any) Plinth 5 Stilt Floor Slab of Super Structure Internal Walls, Internal Plaster, Floorings, Doors, windows within Flats/ Premises Sanitary Fittings within Flats /Premises Staircases,Lift Wells & Lobbies at each Floor Level Overhead and Underground Water Tanks 10 External Plumbing & External Plaster, Elevation, Completion of Terraces, with waterproofing of the Building /Wing Installation of lifts, water pumps, Fire Fighting Fittings and Equipment's as per CFO NOC, Electrical fittings to Common Areas, .electro mechanical equipment's, Compliance to 11 conditions of environment I CRZ NOC, Finishing of entrance lobby/s, paving of areas appurtenant to Building, Compound Wall and all other requirements as may be required to obtain Occupation / Completion Certificate TABLE- B Common Areas (Internal & External Development Works) in respect of the Registered Phase/ Project Number Percentage of Details S.No. Common Areas and Facilities Proposed (Yes/No) Actual Work Done (Ason date of Certifcate) Roads & Footpaths Yes 50% 1 Internal As per Plan 2 Yes 100% Borewell Water Supply 3 Sewerage(Chamber,Lines, Yes 80% Septic Tank Septic Tank, STP) 4 No Storm Water Drains & Tree Planting Yes 50% Trees Landscaping 6 No Street Lighting 7 No Community Buildings Treatment and disposal of No Sewage and Sullage water Solid Waste management & No Disposal Rain Water 10 Water Conservation /Rain 0% Yes Harvesting Water Harvesting 11 Energy Management No 12 Fire Protection and Fire Safety Yes 0% As per Plan requirements 13 Electrical Meter Room, Sub No Station,Receiving Station 14 Others ( Option to Add more) No Agreed & Accepted by: No. Reg. CA2019/115779) Gayatri Builders And Developers RCHITE Parikrama Signature of Promoter Yours Faithfully Name: Gayatri Builders & Developers Signature Date: 31/09/2023 PRIYANKA CHENDULKAR Reg No: CA/2019/115779