AR. PRIYANKA CHENDULKAR B. ARCH Rukhmini Nagar,Amravati Mob: 95454829 11 FORM1 ARCHITECT'S CERTIFICATE To, Date: 30/09/2021 The GAYATRI BUILDERS AND DEVELOPERS (NITIN JUGALKISHOR CHENDULKAR), Subject: Certificate of Cost Incurred for Development of PARIKRAMA GREENS having MahaRERA Registration Number Ps0300011577 (Only applicable after Project Registration)being Developed by GayatriBuilders and Developers. Sir, I/We PRIYANKA CHENDULKAR have undertaken assignment as Architect/ Licensed Surveyor of Certifying Percentage of Completion of Construction Work of Parikrama Greens having MahakERA Registration Number P50300011577(Only applicable after Project Registration) being Developed by Gayatri and Developers. Builders Based on the Site Inspection, with respect to the Layout / each Building/Wing of the aforesaid Real Estate Project, Icertify that as on date of this Certificate, the Percentage of Work Done for each of the Building/Wing of the Real Estate Project under MahaRERA is as per Table-A herein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Table-B. Table A Building /Wing Number 1 in Parikrama Greens (to be prepared separately for each Layout/Building/Wing of Project) Percentage of Actual Work Sr. No. Tasks / Activity Done (Ason date of Certifcate) 1 Excavation 75% 2 Basements (if any) Podiums(if any) Plinth 60% 5 Stilt Floor 45% 6 Slab of Super Structure 20% Internal Walls, Internal Plaster, Floorings, Doors, windows within Flats / Premises 0 Sanitary Fittings within Flats / Premises 9 Staircases, Lift Wells & Lobbies at each Floor Level Overhead and Underground Water Tanks 10 External Plumbing & External Plaster, Elevation, Completion of Terraces, with waterproofing of 0 the Building / Wing Installation of lifts, water pumps, Fire Fighting Fittings and Equipment's as per CFO NOC, Electrical fittings to Common Areas, .electro 11 mechanical conditions of equipment's, environment Finishing of entrance lobby/s. paving | Compliance CRZ NOC, of areas to appurtenant to Building, Compound Wall and all other requirements as may be required to obtain Occupation / Completion Certificate TABLE- B Common Areas (Internal & External Development Works)in respect of the Registered Phase/ Project Number S. No. Common Areas and Facilities Proposed Percentage of Details (Yes/No) Actual Work Done (Ason date of Certifcate) 1 Internal Roads & Footpaths Yes 0% As per Plan 2 Yes Water Supply 100% Borewell 3 Sewerage(Chamber,Lines, Septic Tank, STP) Yes 35% Septic Tank 4 Storm Water Drains No Landscaping & Tree Planting Yes 15% Trees 6 Street Lighting No 7 Community Buildings No Treatment and disposal of No Sewage and Sullage water 9 Solid Waste management & No Disposal 10 Water Conservation / Rain Rain Water Yes 0% WaterHarvesting Harvesting 11 Energy Management No 12 Fire Protection and Fire Safety Yes 0% As per Plan requirements 13 Electrical Meter Room. Sub No Station, Receiving Station 14 Others ( Option to Add more) No Agreed & Accepted by: cyatthi Elea201 Builders And Developers ENDULA TECT Signature of Promoter Yours Faithfully Name: Gayatri Builders & Developers Signature Date: 30/09/202 1 PRIYANKA CHENDULKAR Reg No:CA/2019/115779