AR. PRIYANKACHENDULKAR B.ARCH Rukhmini Nagar,Amravati Mob: 954548291 I FORM 1 ARCHITECT'S CERTIFICATE To, Date: 30/06/2020 The GAYATRI BUILDERS AND DEVELOPERS (NITIN JUGALKISHOR CHENDULKAR), Subject: Certificate of Cost Incurred for Development of PARIKRAMA GREENS having MahaRERA Registration Number P50300011577 (Only applicable after Project Registration)being Developed by Gayatri Builders and Developers. Sir, I/ We PRIYANKA CHENDULKAR have undertaken assignment as Architect/ Licensed Surveyor of Certifying Percentageof Completion of Construction Work of Parikrama Greens having MahaRERA Registration Number P50300011577 (Only applicable after Project Registration) being Developed by Gayatri Builders and Developers. Based on the Site Inspection, with respect to the Layout / each Building/Wing of the aforesaid Real Estate Project, I certify that as on date of this Certificate, the Percentage of Work Done for each of the BuildingWing of the Real Estate Project under MahaRERA is as per Table-A herein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Table-B. Table A Building / Wing Number 1 in Parikrama Greens (to be prepared separately for each Layout/Building/Wing of Project) Percentage of Actual Work Sr. No. Tasks / Activity Done (As on date of Certifcate) Excavation 75% 2 Basements (if any) 3 Podiums (if any) 4 Plinth 60% 5 Stilt Floor 45% Slab of Super Structure 20% Internal Walls, Internal Plaster, Floorings. Doors. 7 windows within Flats / Premises 8 Sanitary Fittings within Flats / Premises Staircases, Lift Wells & Lobbies at each Floor Level Overhead and Underground Water Tanks 10 External Plumbing & External Plaster, Elevation., Completion of Terraces, with waterproofing of the Building / Wing Installation of lifts, water pumps, Fire Fighting Fittings and Equipment's as per CFO NOC, Electrical fittings to Common Areas, .clectro - mechanical equipment's, Compliance to 11 conditions of environment / CRZ NOC, Finishing of entrance lobby/s, paving of arcas appurtenant to Building, Compound Wall and alI other requirements as may be required to obtain Occupation /Completion Certificate TABLE -B Common Areas (Internal & External Development Works) in respect of the Registered Phase/ Project Number S.No. Common Areas and Facilities|Proposed Percentage of Details (Yes/No) Actual Work Done (Ason date of Certifcate) 1 Internal Roads & Footpaths Yes 0% Asper Plan 2 Water Supply Yes 100% Borewell 3 Sewerage (Chamber,Lines, Yes 35% Septic Tank Septic Tank, STP) 4 Storm Water Drains No Landscaping & Tree Planting Yes 15% Trees 6 No Street Lighting 7 No Community Buildings 8 Treatment and disposal of No Sewage and Sullage water Solid Waste management & No Disposal Rain Water 10 Water Conservation /Rain Yes 0% Water Harvesting Harvesting 11 |EnergyManagement No 12 Fire Protection and Fire Safety Yes 0% As per Plan requirements 13 Electrical Meter Room, Sub No Station, Receiving Station 14 Others ( Option to Add more) No Agreed & Accepted by: NCHEN (P Gayatri Builders And Developers CHITEC Parikrama Signature of Promoter Yours Faithfully Name: GayatriBuilders & Developers Signature Date: 30/06/2020 PRIYANKA CHENDULKAR Reg No: CA/2019/115779