Annexure E FORM 4 (See Regulation 3) ARCHITECT’S CERTIFICATE (To be issued on Completion of Registered Project) Date: - 19/04/2023 To, Shri. Vinod Sumantrao Ugemuge (V. M BUILDERS & DEVELOPERS) Plot No. 1282/1, Sheet No. 49, Vibhag No. 1.38, Sudampuri, Wardha, 442001. Subject: Certificate of Completion of Construction Work of “Nalini – Sumant” Having Bearing MahaRERA Registration No. “P50400010094” being developed by V. M BUILDERS & DEVELOPERS (Shri. Vinod Sumantrao Ugemuge) Sir, I, Er. Vikas Laxman Golait have undertaken assignment as an Architect / Licensed Surveyor of Certifying Completion of Construction Work of “Nalini – Sumant” having Bearing MahaRERA Registration Number. “P50400010094” being developed by V. M BUILDERS AND DEVELOPERS (Shri. Vinod Sumantrao Ugemuge). I hereby certify that, on basis of my inspection and certificate received from Structural Engineer and Site Supervisor, the following area of “Nalini – Sumant” has been completed in all aspects of Building and is fit For occupancy for which it has been constructed and enlarged. Further the following Occupancy Certificates/Completion Certificate have been granted: Sr. Occupancy Layout And Building Number Date Local Planning No. Certificate Number Authority 1 CAWRM/FO/2023/ “Nalini–Sumant”, Plot No. 1282/1, 05/04/2023 Municipal Council, APL/00004 Building No. 01, Sheet No. 49, Wardha. Vibhag No. 1.38, Mouza : Wardha I Certify that the Project “Nalini – Sumant” having Bearing MahaRERA Registration Number “P50400010094” is complete in all aspects of building as per Agreement of sale. Yours faithfully, Agreed and accepted by: V. M BUILDERS & DEVELOPERS Er. Vikas Laxman Golait (Prop: Vinod Sumantrao Ugemuge). (License Number: 1004) Date: 19 / 04 / 2023 Date: 19 / 04 / 2023 Note: I had issued Completion Certificate in Form 4 to promoter on January 27, 2023, after verification of the project, in the said certificate it is mentioned that, the promoter had applied for Completion certificate / Occupancy certificate on December 15, 2022, to local authority (i.e. Municipal Council, Wardha.). Therefore on the request of the promoter I, hereby issued revised certificate in Form 4 mentioning the details of Completion Certificate / Occupancy Certificate as the copy of the same is produced before me for verification.