A ATUL BANG B. ARC H, A,I,I,A, Approved Valuer Regd.Arch.No.Ctu92l1 5464 Government Approved Regd. Valuer ARC H ITECT,I N TE RI OR, Cat 1/8iof 2002-03 LANDSCAPE OESIGNER A For lncome Tax, Wealih Tax GOVT. APPROVED VALUER a Annexure A FORM.1 ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) Date: 01/ 10 / 2023 to 3L / 12/2023 To, Subject : Certificate of Percentage of Completion of Constructior-r Work of Project "Shakambari Centro" having Maha RERA Registration No. REA50100129880, being developed by Shri. Sushilkumar Ratanlal Khowal. Sir, I have undertaken assignment as an Architect of certifying Percentag of Completion of Construction Work of the Project Shakambari Centro having RERA Number- REA50100129880 being developed by Shri. Susl-rilkumar Ratanlal Khowal. Based on Site Inspection, with respect to each of the Building of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the building of the Real Estate Project under Maha RERA is as per Table A here in below. The percentage of the u,ork executecl l.ith respect to each of the activity of the entire phase is detailecl in Table B. "8.8.C." Adarsh Cotony, N6ar Old lncome Tax Office, corakshan Road, Akola 444 004, Phone : 245862'1 (R), Cell : 942216M88, E-mail : atul-bang@yahoo.com A ATUL BANG B.ARCH, A,I,I.A, Approved value. Regd.Arch. No. CA/g2l 15464 Government Approved Regd. Valuer ARCHITECT,INTERIOR, Cal 1 l8bf 2002-03 LANDSCAPE DESIGNER & For lncome Tax. Wealth Tax GOVT. APPROVED VALUER TABLE-A Percentage of work done (As on date of this Excavation 100 % Basements (if any) Pcxliums (if any) Internal walls, Internal Plaster, Floorilrgs witl'rin Flats/Premises, Doors and Windon s to each of Sanitary Fittings within the Flat/ Premises, Eiectrical Fittings within the Flat/Pren-rises 85% Staircases, Lifts Wells and Lobbies at each Floor level connccting Staircases ar-rd Lifts, Overhcarl 90 "/. and Undersround Water Tanks The external plumbing ancl external elevation, completion of terraces 95% waterproofing of the Builcling/Wing, Installation of lifts, water punlps, Fire Fighting Fittings and Equipmcnt as per CFO\OC, Electrical fittings to Common Areas, electro, o., ol mechanical equipment, Compliarrce to conrlitions of environment/ CRZ NOC, Finishing tcr enh'ance lobb.v, plinth protection, paving of areas appurtenant to Builcling/ Wing, Compound \,Vall ancl al1 other requirements as mav be requirecl to Obtain Occupatior-r letion Certificate "8.8.C." Adarsh Colony, Near Old IncorI€ Tax Office, Gorakshan Road, Akola 444 004, Phone : 2458621 (R), Cell : 9422160488, E-mail : atul-bang@yahoo.com A ATUL BANG B, ARC H, A,I,I,A, Approved Value. Regd.Arch. No. CA/92l 1 5464 Government Approved Regd. Valuer ARCHITECT,INTERIOR, Cat l lalol 2002-03 LANDSCAPE DESIGNER & For lncome Tax. Wealth Tax GOVT. APPROVED VALUER TABLE-B Internal & External Development Works in ResplglqlUtE-ggtilg Registered Phase o Lommonareas Proposed Percentage of Details andFacilities, (Yes/ No) Actual Workdone Amenities (As on date of this certificate) No ater Supp Yes 90% Bore Well/ I Corporation Water Sewarage Scptic Tank is (chamber, lines, Septic Yes 88% proviclccl. Tank , STP) ater Yes 100 % Sump Tank I is provided. Lanclscaping & Tree No Planting Street Lighting No 7. Community Buildings No Treahnent and disposal of No sewage and sullage water 9. Solicl Waste management No & Disposal Water conservation, Il Yes 100 % Rainu,ater water harvesting Harvesting \o Yes 85% safety requirements meter room, \o station, receiving station Others (Option to , Yes 95 % Electric meters panel ; Add more) is provitled. Yours Faithfully Sigra sig.atureofPromoter J'kl'A"''"'l \anrc o[ Ar \ame: SIIRI. SUSHII.KU\1AR RATANLAL KHOIVAL l-ice.nst, \r'r: Date: 20/01/202.1 Place: Akol.r. ,,8.8.C.. I atul-bang@yahoo c'm Adarsh Cotony, Near Otd lncome Tax Office, corakshan Road, Akola 444 OM, Phone : 245862'1 (R), Cell : 9422160488, E"mail