FORM -2A ENGINEER,S CERTIFICATE FOR qUALITY ASSURANCE I Site Supervisor 's certificate] To, Date :- 15.04.2022 M/s Dream Constructions Tapadiya Nagar Akola. QualiW Assurance Certificate lCertificate No. 01 for the Quarter ending March 20221 Subject: Certificate for quality of materials used and quality of Construction and workmanship for the work of Building "Prime Towe/' having Maha RERA Registration Number P501O0O33195 being developed by M/s Dream Constructions Sir, I Anurag Agrawal have u ndertaken an assign ment of su pervision of this real estate project. . Our Responsibility To carry out the work in accordance with the development permission and as per the approved plan and submit certificate of supervision of work and to carry out material testing in -situ or in the authorized laboratory and to ensure quality of work and workmanship as per prescribed specifications, and as per NBC and or other relevant code of practice. 1. lnput Materials, Fixtures and Fittings l/We hereby certify that all Construction material, Fixtures and Fittings with regard to the flooring. Electrical, Sanitary fittings etc and amenities to be provided by the Promoter in the said Project, building and the Apartment as are as per specifications mentioned in Annexure 'F', of Agreement of Sale. For those items, where no specifications have been mentioned in agreement of sale, the materials, Fixtures and Fittings used conform to the relevant BIS Standards / lS /Nationar Buirdingcodesorasperindustrystandards. x* \, 2. Workmanship - l/we hereby certify that work has been carried out under our supervision. we further certify that workmanship and quality is satisfactory and up to the mark and the work has been acceptable within the permissible limits of deviations as per relevant code of practice. 4. Structural engineerr Promoters has engaged structural engineer shri Ajay lohia of A.J. tohiya & Associates having Licenses noDDMCo/R/2O2olApLloo2tL having office no o724-24sszs6 & cell no 9422a62357. The structural design of buildings in this project has been done under his supervision . The formwork and concrete mix design has been done as per ls 10262:2009 or as per other relevant codes as applicable. His periodic checks and certificates for srABlLlw and SAFETY have been kept on record. 5, Preservation of records:- Record of all test results ofthis project have been properly kept in the prescribed formats and will be preserved at least up to the defect liability period or for the period as required by any other provision of law. Please specify deviation in quality of materials or any other item of work which were not conforming to the specifications as mentioned in Agreement of Sale -None Yours Faithfully, \KC/ Anfag Sffiram Agrawal il ( B.E. Civil , AMIE, Flv ) Regd No.: AMClt4l20L7 Ramnagar, Akola -444001 Mob. :- 94231 t14398 Email :- anurag.consultant@gmail.com Agreed and accepted By .Ani,trag Aara:nthf L,\ Sanjay Kum\r Agrawal H.,.1, i ' :,.r.. '):' 't' l:'€' FIV ,'lDZEESdmt. F{amnagar; Ai\Uu, l,ioo.: 94231.143S1 Partner- Dream Constructions Date - 15.04.2022