Architects & Interior Designers Ishwar Anandani B.Arch. , AIIA Padia Complex , Tower Chowk, Akola 444001 Cell +91 98220 35263 * CA 92/15251 * IIA 9959 ___________________________________________________________________________ TO WHOMSOEVER IT MAY CONCERN ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) Date :31st May 2025 To The MR VINOD PANJWANI AND OTHERS Subject : Certificate of Percentage of Completion of Construction Work of AKOLA TEXTILE MARKET ( ATM ) No. of Building(s)/ BLOCK A AND B Wing(s) of the CIVIL WORK COMPLETED and BLOCK “D “ 50% of civil work completed ofthe Project [Real Estate Regulatory Authority, Maharashtra Registration Number] situated on the Plot bearing survey no.73/2 Final Plot no 01/02/03 demarcated by its boundaries ( latitude and longitude of the end points) to the North_ to the South to the East _ to the West, of village T e h s i l AKOLA District AKOLA and measuring 16892.77 sq.mts being developed by MR. VINOD PANJWANI AND OTHERS Sir, I/ We AR. ISHWAR ANANDANI have undertaken assignment as Architect of certifying 70% Percentage of Completion of Construction Work of the ATM Building(s)/ A AND B and 50% work of Block “ D”Wing(s) of the 1st Phase of the Project, situated on the plot bearing survey no 73/2 Final Plot no of 01/02/03 village AKOLA Tehsil AKOLA District AKOLA 1 PIN and measuring 16892.77 sq.mts. area being developed by MR. VINOD PANJWANI AND OTHERS Following technical professionals are appointed by Owner / Promoter :- Shri AR. ISHWAR ANANDANI Architect SHRI AMIT MAHAJAN a Structural Consultant M/s /Shri / Smt as MEP Consultant SHRI AJAY MAHAJAN as Site Supervisor Based on Site Inspection, with respect to each of the Building/Wing of the aforesaid Real Estate Project , I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project as registered vide under Real Estate Regulatory Authority, Maharashtra is as per table A hereinbelow. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. 2 Table A Building /Wing Number A, B AND D (to be prepared separately for each Building /Wing of theProject) Sr. No Tasks /Activity Percentage of work done 1 Excavation A AND B 70% CIVIL WORK COMPLETED BLOCK D 50% WORK COMPLETED 2 NO OF PLINTH 3 3 NUMBER OF PODIUMS NO 4 STILT FLOOR NO 5 Number of slabs of super structure 10 6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks 9 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing, 10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation / Completion Certificate 3 TABLE-B Internal & External Development Works in Respect of the entire Registered Phase S.No Common areas and Proposed Percentage of Work Details Facilities, Amenities (Yes/No) done 1. Internal Roads & YES 50% RCC Foothpaths 2. Water Supply 4 BOREWELL COMPLETED 3. Sewarage (chamber, YES NOT DONE YET lines, Septic Tank , STP) 4. Storm Water Drains YES NOT DONE YET 5. Landscaping & Tree YES NOT DONE YET Planting 6. Street Lighting YES 7. Community Buildings 8. Treatment and YES NOT DONE YET disposal of sewage and sullage water 9. Solid Waste YES NOT DONE YET management & Disposal 10. Water conservation, YES NOT DONE YET Rain water harvesting 11. Energy management YES NOT DONE YET 12. Fire protection and YES NOT DONE YET fire safety requirements 13. Electrical meter YES NOT DONE YET room, sub-station, receiving station 14. Others ( Option to Add more) Yours Faithfully AR. ISHWAR ANANDANI REG. NO. CA 92/15251 13 14