santosh thole assoclates archtoct & intorior designer FORM 1 [seeRegulation 31 ARCHITECT'S CERTIFICATE To Date: 01 August 2023 BG Steel and Infra Bilala's, Near Saint Anns School, Geeta Nagar, Akola-444002. Subject: Certificate of Percentage of Completion of Construction Workof Bill Mart having MahaRERA Registration Number P50100021239 being developed by BGSteel and Infra. Sir, , Santosh M. Thole, have undertaken assignment as Architect /Licensed Surveyor of certifying Percentage of Completion of Construction Work of having MahaRERA Registration NumberPS0100021239 being developed by BGSteel and Infra as on 31-07-2023. Based on Site inspection with respect to Layout / each of the of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project under MahaRERA is as per Table A herein below. Percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table 8. TABLE-A Layout / Building Wing Number A, B, C, D and E of common building as per revised building permission Bearing Permit No. DDMCO/ RB/2023/APL/O0286 Dated 14.07.2023. Sr No Tasks / Activity Percentage of Actual Work Done (1 (2) (As on date of this Certificate) (3) 1. Excavation 95% 2, Basement's (if any) 100% 3 Podiums (if any) 4. Plinth N.A. Stilt Floor 95% Slabs of Super Structure N.A. 7. Internal walls, Internal Plaster, Floorings, I) 90% windows within Flats/Premises doors and 85% 8 Sanitary Fittings within the Flat/Premises Staircases. lifts' Wells and Lobbies at each 25% Overhead and Underground Water Tanks Floor level 70% 10 External plumbing and external plaster, elevation, completion of terraces with waterproofing of the 70% Building/wing. Add: 31,32, 1st floor, nirala bazar, above ashoka's ph: 9422291681 - email: ar.santoshthole@ymail restaurant,aurangabad-431001 com com | website: www.architectsantoshthole. santosh thole associates atgRe ct & interio designer 11 Installation of Lifts. water purmps, Fire Fitting Fittings and Equipment as per CFO NOc, Electrical fittings, mechanical equipment, compliance to conditions of environment/CRZ NOc. Finishing to entrance lobby/s. plinth protection, paving of areas appurtenant to Building/Wing. Compound Wall and al other requirements as may be required to complete project as per specifications in agreement of Sale. Any other activities. TABLE-B Common Areas (Internal and External Development Works) in respect of the Registered Phase/Project Number Sr Common areas and facilities Propos Percentage Details No ed of Actual (1) (2) (Yes/N Work Done (S) o) (As on date (3) of the Certificate) (4 1. Internal Roads &Footpaths No 30% 2. Water Supply Yes 30% 3. Sewerage (Chamber, lines, Septic Tank, STP). Yes 0% 4. Storm Water Drains Yes 0% 5. Landscaping &Tree Planting Yes 0% 6. Street Lighting Yes 0% 7. Community Buildings No 0% Treatment and disposal of sewage and sullage water. Yes 0% Solid Waste management &Disposal Yes 0% 10 Water conservation/ Rain water harvesting Yes 0% 11 Energy management. Yes 0% 12 fire protection and lire Safety requirements Yes 0% 13 Electrical meter room, sub-station,receiving station. Yes 0% Separate DP Proposed 14 Others (Option to Add more) Your's Faithfully, Agreed and Accepted by: B.G. Steel and lnfra ForBG Steel and Infra. Santosh M. Thole Partner Date:01/08/2023 Architect license No.CA/92/14846 Add: 31,32, 1st floor, nirala bazar, above ashoka's restaurant,aurangabad-431001 ph 9422291681 -email: ar.santoshthole@gmail.com website wwW.architectsantoshthole com