Clarifications in relation to reason mentioned by Maharera in relation to Project Completion Application Rejection: 1. Kindly update the FSI/ floors / units / parking data correctly as per plan in original application as per OC plan / final approved plan through correction module. Mundada Realty Comments: Dear Sir, In relation to same we submit that the FSI/Floors/Units/Parking Data are already updated as per Final Plan Approved. We wish to submit that the Project had underwent a FSI Change in February 2025 after which we had duly filed for Correction Application vide our Application No. PCRCN23052511879 which we duly accepted by Maharera and post which there has been no change in Plan and thus all the data appearing on maharera website is as per latest plan dated 14.02.2025 which is already verified and approved by Maharera. The FSI Reconciliation as per said plan is shared: Exisiting Builtup Area as per Plan: Total Sanctioned Area: Existing FSI Area 5741.69+2783.099(9.4 Total Permissible PLine Area) =8524.79 Proposed Builtp Area: Existing FSI Area 5741.69+2757.180 (9.4 Total Permissible PLine Area) =8498.87 2. Kindly upload last approved plans / plans issued along with OC. Mundada Realty Comments: Dear Sir, The latest approved plan dated 14.02.2025 are already available on Maharera Website under Technical Details Tab. The screenshot of same is produced below and highlighted: Even the Final OC Provided confirms that the final completion has been granted on basis of Plans dated 14.02.2025, the relevant part is produced below: 3. Please refer UD's resolution dated 23.02.2023 and subsequent MahaRERA order u/no 45 of 2023 dated 15.05.2023, Verification of O.C. is yet to be received. Mundada Realty Comments: Dear Sir, We have duly uploaded the screenshot of Mail sent by Sanctioning authority to Maharera in the PDF Attachment uploaded in relation to Completion. Please refer all the pages of PDF. The screenshot is again produced below: