FORM 1 ARCHITECT'S CERTI FICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account - Building/Wing wise) To Date:L4/04/2021 N&L Associates, 56, Shivram Nagar, M.J. College Road, Jalgaon-425001. Subject: Certificate of Percentage of Completion of Construction Work of "SHREE SAI SONA PLAZA"Building(s)One of the Building /Phase of the Project Maharera Registration NumberP49900019598situated on the Plot bearing c. N. No / cTs No.1597A/191L + t6971L912, Jalgaon demarcated by its boundaries (latitude and longitude of the end points) 4.50M Road to the North, CTS No.1697Al2O to the South, 10 M Wide Road to the East, Lane to the West of at Mahabal, Taluka/District Jalgaon PIN 425001 admeasuring 318.60sq.mts. Area being devetoped by N&L Associates. Sir, l/ we Anand Amol Mukundhave undertaken assignment as Architect / Licensed Surveyor of certifying Percentage of Completion of Construction Work of the"SHREE SAI SONA PLAZA" Building(s)One of the Building /Phase of the ProjectMaharera Registration Number P49900019598situated Plot bearing C. N. No / CTS No.1697A/19/t + 1697/19/2. Jalgaon of Division Jalgaon Village Jalgaon Taluka and District Jalgaon PIN 425001admeasuring 318.60 sq.mts. Area being developed by N&L Associates. 1. Following technical professionals are appointed by Owner / Promoter:- (i) Shri. Anand Mukund as Structural Consultant and Architec! (ii) Shri. Sagar Subhash Ingale as Site Supervisor: (iii) Shri. Hemant Jagnnath Nyati as a quality assurance supervisor; Based on Site Inspection, with respect to each of the Building / Wing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the building / Wing of the Real Estate Project as registered vide number Maharera Registration Number P49900019598 under RERA is as per table A herein below. The percentage of the work executed with respect to each of the major activity of the Building / Wing and Overall Percentage of the work done with respect to each Building / Wing is detailed in the Table B. Table A Sr.No Tasks / Activity Percentage t Excavation rc0% 2 Plinth rc0% 3 RCC- Slabs of SuperStructure n0% 4 Masonry/walls -Completed r00% 5 Internal Plaster -Completed t00% 6 ExternalPlaster, elevation- In progress r00% 7 Flooring within Flats / Premises-ln progress r00% 8 Door and Windows to each of the Flat / Premises r00% 9 External plumbing down take lines,CPl Sanitary Fitting within the r00% Flats / Premises- Electrical Fitting within the Flats / Premises, 10 Electrical switches and wiring inside apartment r00% 11 Painting rc0% L2 Staircases, Lifts Wells and Lobbies at eachFloor level connecting 100% Staircases and LiftsOverhead and Underground Water Tanks 13 Completion of terraces with waterproofing of the Building 100% t4 Installation of lifts r00% 15 Fire Fighting Fittings and Equipment's as per CFO NOC r00% t7 Electrical fittings to Common Areas, water pumps,electro - 100% mechanical equipment's 18 Finishing of entrance lobby/s, paving of areas appurtenant to t00% Building, Compound Wall and all other requirements as may be required to obtain Occupation / Completion Certificate TABLE -B Internal & External Development Works in Respect of the project S. No. Common Roads and Facilities, Amenities 'Proposed Percentage of Work Details (Yes/No) done t Side margin pavement No 0% 2 Water Supply Yes 100% 3 Sewerage (chamber, sewage lines), Yes r00% Storm Water Drains 4 Landscaping & Tree Planting No 0% 5 Common area Lighting No 0% 6 Water conservation, Rain water Yes t00% harvesting 7 Fire protection and fire safety No 0% requirements 8 Electrical meter room, sub-station, Yes 0% receiving station Reg.No.J.M.C021 Add ress :-lsrMayu reshAppa rtment Ring Road, Jalgaon-425001 Contact No:-9326299499 A${ANffi A" IWIJ S{T} fifi.E.(Stru 6'si