Pratlk Prakash Badgujar 9 Dhule ■ badgujar.pratik@gmail.com □ 8087999987 Forml (See Regulation 3) ARCHITECT'S CERTIFICATE Date: 21/06/2026 To, Chuadhari and Badgujar Associates Deopur, Dhule, Maharashtra 424002. Subject: Certificate of percentage of completion of construction work of "Narayani Apartment" having MahaRERA Registration Number: P49800080221 being developed by Chaudhari and Badgujar Associates Sir, I / We Pratik Prakash Badgujar have undertaken assignment as Architect/Licensed Surveyor of certifying percentage of Completion of Construction work of the"Narayani Apartment"having MahaRERA Registration Number: P49800080221being developed by Chaudhari and Badgujar Associates Based on site Inspection, with respect to layout/each of the building/wing of the aforesaid Real Estate project I certify that as on the date of this certificate, the percentage of work done for each of the building/ wing of the Real Estate project under MahaRERA is as per table A herein below .The percentage of the work executed with respect to each of the activity of the entire phase is detailed in table B. Table A Layout/Building/Wing No._ _ (fo be prepared separately for each layout/building/wing of the project) Sr. No. Task/Activity Percentage of actual work done (As on 31.03.2026) (1) (2) (3) 1. Excavation 100% 2. Basements (if any) 0 0 ~- Podiums (If any) 0% ~- Plinth 5. Stilt Floor 0% 6. Slabs of Super Structure 100% 7. Internal Walls ,Internal Plaster, Floorings, Doors and Windows 100% Within Flats /Premises 8. Sanitary Fittings Within the Flat/Premises 90% 9. Staircases, Lifts Wells and Lobbies at each Floor level overhead 90% Underground Water Tanks 10. External plumbing and external Plaster, Elevation, completion of 90% terraces with waterproofing of the building/ wing. 11. Installation of Lifts,Water pumps ,Fire Fighting Fittings and 0% Equipment as per CFO NOC, Electrical Fittings, Mechanical Equipments ,Compliance to conditions o f environment / CRZ NOC Finishing to entrance Lobby/ s,plinth Protection, Paving of areas appurtenant to Building/Wing,Compound wall ~d all other requirements as may be required to complete the project as per specifications in agreement of sale. Any other activities. Table B Common Areas (Internal & External Development Works)in respect of the registered phase /project number ~r.No. Common areas and Proposed Percentage of Details Facilities, Amenities (Yes/No) Actual Work Done (As on 31.03.2026) (1) (2) (3) (4) (5) 1. Internal Roads and No 0% NA Footpaths 2. Water Supply Yes 0% Borewell And NMC Water Connection 3. Sewerage (chamber, Lines, Yes 0% NoSTP Septic Tanl<, SI'P) 4. Storm Water Drains No 0% NA 5. Landscaping &Tree Planting No 0% NA 6. Street Lighting No 0% NA 7. Community Buildings No 0% NA 8. Treatment and Disposal of No 0% NA Sewage and Sullage water 9. Solid WasteManagement & No 0% NA Disposal 110. Water Conservation/Rain Yes 0% Only Rain Water Waterharvesting Harvesting 11. EnergyManagement No 0% NA 12. Fire Protection and Fire No 0% NA SafetyRequirements 13. Electrical meterroom, Sub- No 0% NA Station, Receiving station 14. Others (Option to Add more) No 0% NA Yours Faithfully Pratik Parakash Badgujar (License No ...................) ~Q,•. •at~ Agreed and Accepted by: • ?,.~-,,.6.~~\l ~'b-'(\ »'b-~~ ~ Name: Chaudhari and Mdgujar Associ~6 _,_...,....__. Designation: Authorised Signatory Date: 21.06.2026 ~ Place: Dhule ~ J