I L rol Ocsign Su pc rvision FORM NO.1 ( See Regulation 3 ) ARCHITECTS CERTIFICATE (To be submitted at the time of Registration of Ongoing Projecl. Ouarterly Progress Reporting and for withdrawat ot money from designated account) Date 06.06.2022 o Nilcon lnfrabuilders Private Limited Dhule - 424001 Subjecr : Certificate of Percentage of Completion of Construction Work of Project THE HORIZON (RERA Registration Number Apptied ) developed by Nilcom lnfrabuilders Private Limited. Sir, I Raiendra S Chhajed have undertaken assignment as Architecl of certrying percentage of Complelion of Construclion Work of the HORIZON Plot No.04, Near S.No.38 ofi Division Nashik, Village Deopur, Dist Dhule - 424005, having MAHARERA Registration being developed by NilcDn lnfrabuilders Private Limited. Based oo site lnspectron. with respect to each of the Buildings of the aforesaid Real Estate project. I certify that as on the date of this certiflcate, percentage of work done for each of the Buildings of the Real Estate Project as registered vide number Applied under RERA is as per herein below. The percentage of the work executed with respect to each of the msjor activity of the Building and Overall percentage of done with respeci to each Building is detailed in the Table B. 5-A, Wakha*ar Nagar, Behind NatralTalkies, DHULE - 424 001 Tel. : 02562 - 231680, 309380 $ffii - au 'fl Table A Buildir€ - TllE I{ORIZON Date 06.06.2022 Sr Tasks / Activity Target dates (at time Actual work executed (as on date of certificate) No. of registratbn of Start date Completio Siart date Completio Percentage of n date n date work done. 1 -34-5-6 -7 'l Excavalion 01 .09.2021 30. 1 1 .2021 10.09.2021 28. 1 1.202 100o/o 1 2 Basemenls 01 2.2021 31 2.2021 01 2 2021 31 2 202 .1 .1 .1 1 1oo% 1 3 Podiums NA NA NA NA NA a Plinth 12.2021 31 .12.20214.12.2021 28.12 202 1io'/" 5 Stilt Floor 01 .01.202231 .01 .2022 05.01 .20221 5.02.202 1w% 2 6 Slabs of Super Structure Ol .02.2022 31 .08.2022 8.02.2022 1 lsito 7 lnternal Walls, lntemal Plaster, Floorings 01 06 202 31 .10 202201.06.202 {% within flats / premises, Doors and Windows 2 2 to each of the flat premises. 8 Sanitary Fittings within the Flat /Premises, 01 11 202 31.12.2022 o;t" Electrical Fittings within the Flat Premises. 2 9 Staircases, Lifts Wells and Lobbies at each 01 .06.202 30.09.2022 156/o floor level connecting Staircases and Lifts, -2 Overhead and Underground Water Tanks. 10 External Plumbing and external Plaster, 01 .02.202 30.04.2023 V/" Elevation, completion of Terraces with 3 Waterproofing of the Building / Wing. 1 1 lnstallation of Lifts, Water Pumps, Fire 01 05.202 31.07.2023 Oo/o Fighting Fittings and Equipments as per 3 CFO NOC, Electrical Fittings to common area, Elec{ro, Mechanical Equipments, compliance to conditions of environment I CRZ, NOC, Finishing to Entrance Lobby/s, Plinth protection, Paving of areas appurtenant to Building / Wing Compound wall and all other requirements as may be required to complete the project as per 12 Overall percentage of physical work done \glut9, 2 -r=h dE \ TII.J i Plons & Supcrvision Table B Building - THE HORIZON Date 06.06.2022 Common Areas (lnternal & External Deployment Work) in respect of the entire Registered Phase Sr. Common areas and Facilities, Proposed Target dates (at time Actual work executed (as on date of certilicate) No. Amenities (Yes/No) of registration of Start date Completio Slart date Completio Percentag Details n date n date e of work -1 -3 4 -5 -b -7 -8 -9 1 lnternal Roads & Footpaths No NA NA NA NA NA 2 Water Supply Yes 01 .08.2023 31 .08.2023 0o/o MUNCTPAL wArER 3 Sewerage (Chamber, Lines, Yes 01 .06.202231.08.2023 SEPTIC TANK Septic Tank, STP) 4 Storm Water Drains . No NA NA NA NA NA 5 Landscaping & Tree Planting No NA NA NA NA NA 6 Street Lighting No NA NA NA NA NA 7 Community Buildings No NA NA NA NA NA .'i,r $d Wakhartar Nagar, Behind NatraiTalkies, oHULE - 424 001 Tel. : 02!5Qt - rn --r-l Sr. Common areas and Fei[ties, Proposed Target dates (at time Actual rvork executed (as on date of certificate) No. Amenit'Es (YeJNo) of registration of Start date Completio Start date Completio Percentag Details n date n date e of work 1 -2 -3 -4 -5 -6 -7 -8 -9 8 Treatment and Disposal of No NA NA NA NA NA Sewage and Sullage Water I Solid Waste management &D,st No NA NA NA NA NA 10 Water Cons€rvation, Rain Yes 01 .09.2023 30.09.2023 RAIN WATER water Harvesting. HARVESTING 11 Energy management Yes 01.10.202331j2.2023 SOALR PANEL 12 Fire Protection and Fire safety No NA NA NA NA NA requiremenls. 13 Electrical meter room. Sub- No NA NA NA NA NA station, Receiving station '14 Others ( Option to Add more ) No NA Yours Faithfully, IAIES RAJENDRA S.CHHA coilsl,trric E*BtxGER,3 REOD NO It! sr^.r{ora8xAn f oAt,otrfi.E ro8.taaapol,a.81180