VASTU RACHANA ASSOCIATE Architectutal Design & Supervision Add : 5-A, Wakharkar Nagar , Behind Nahaj Talkies, Dhule 42t1001 FORM - 2 (See Regulation 3) ENGINEER'S CERTIFICATE (To be submitted at the time of Registration of ongoing Proiect and for withdrawal of Money from Designated Account-Proiect wise) Date:06052025 To, Vrundavan Buildcor! Shri Krishna Marbal Compound, Parola Road, Opp. Cotton Market, Near APMC, Dhule, Nashik- 424 004. Subjecx Certificate of Cost Incurred for Development of "Vrundavan Plaza" having MahaRERA Registration Number :P4980011285 being developed by Vrundavan Buildcon. S l I Er . Raiendra Chhaied have undertaken assignment of certifying Estimated Cost for "Vrundavan Plaza" having MahaRERA Registration Number: P4980ffi11285 being developed by Vrundavan Buildcon. we have estimated the cost of civil. MEP and allied works required for completion o{ the apalEnents and proportionate completion of intemal & extemal works of the project as per specifications mentioned in agleement of sale. our estimated cost calculations are based on the drawings/plans made available to us for the project under reference by the Developer / consultants. The schedule of items and quantity required for the entire work as calculated by Quantity Surveyor* appointed by Developer/Engineer, the assumption of the cost of material, labour and other inputs made by developer, and the site inspection carried out by us to asceltain / confirm the above analysis given to us. 3. we estimate Total Estimated Cost of completion of the aforesaid project under reference at Rs.69,50,500/- (Total of Table A and B) at the time of Registration. The estimated total cost of project is with reference to the Civil, MEP and allied works required for completion of the apartments and proportionate completion of intemal & extemal works, as per specifications mentioned in agleement of sale and for the purpose of obtaining occupation certificate/ completion certificate for the building(S) / Wlng(S) / Layout / Plotted Development from the Dhule Municipal Corporation being the planning authority under whose jurisdiction the aforesaid project is being implemented. 4. The estimated Cost Incurred till31.03.2024 is calculated at Rs.52,51,300/- (Total of Table A and B). The amount of Estimated Cost Incurred is calculated on the basis of input materials / services used and unit cost of these items. 5. The Balance cost of Completion of the Civil, MEP and Allied works for completion of the apartments and proportionate completion of internal & external works, as per specifications mentioned in agreement of sale, of the project is estimated at Rs|1,6,99,200/- (Total of Table A and B). 6. I certify that the cost of the Civil, MEP and allied work for the apartment and proportionate internal & external works, as per specifications mentioned in agreement of sale, of aforesaid Project as completed on the date of this certificate is as given in Table A and B Below: Table A Building/Wrng/Layout/Plotted Development bearing Number L or called Vrundavan Plaza (To be prepared separately for each Building /Wng/Layout/Plotted Development of the Real Estate Project) Sro No。 Particulars Amounts (In Rs.) 1 Total Estimated cost of the 65,00,000/- building/ w rng/ Lay outl Plotted Developments as 2 Cost incurred as on 31,.03.2024 52,51.,300/ - 3 Work done in percentage (as percentage of the 80.79% estimated cost) 4 Balance Cost to be Incurred**(Based on 12,48,700/ - Estimated Cost) 5 Cost incurred on additional / Extra Items not NA included in the Estimated Cost (Table-C) Table B Internal & External Development Works In Respect of the Registered Phase Sro No. Particulars Amounts (In Rs.) 1 Total Estimated cost of the Intemal and 4,50,500/- External Development works including amenities and facilities in the layout 2 Costincurred as on 31.03.2024 0.00 3 Work done in percentage (as percentage of the 0% estimated cost) 4 Balance Cost to be Incurred (Based on 4,50,500/- Estimated Cost) 5 Cost incurred on additional / Extra Items not included in the Estimated Cost (Table-C) WASTU RACHANA ASSOCIATES RA,ENDRA S.CHHA,ED CONSULTING ENGINEER'S REGD N0 010 51A,WAKHARKAR NAGAR,OHULt 。2316鴫 MOB。 9422289905,審 Agreed and Accepted bY: Name: Vijay Narayan Bhadlikar Date:06.05.2025 Note: L. The scope of work is to complete Registered ReaI Estate Project as per Drawings approved from time to time and as per specifications mentioned in agreement of sale. 2. (.) Quantity survey can be done by office of engineer or can be done by "n independent euantity Surveyor, whose Certificate of quantity calculated can be relied uPon by the Engineer. In case of independent quantity surveyor being appointed by Developer, the name has to be mentioned at the place marked (.) and in case quantity are being calculated by the Engineer, the name of the person in the office of Engineer, who is responsible for the quantity calculated should be mentioned at the place marked C). 3. C.) Balance Cost to be incurred (4) may vary from Difference between Total estimated Cost (1) and Actual Cost incurred (2) due to deviation in quantity required / escalation of cost etc. As this is an estimated cost, any deviation in quantity required for development of the Real Estate Project will result in amendment of the cost incurred/ to be incurred. 4. All components of work with specifications are indicative are not exhaustive' 5. Please specify if there are any deviations / qualifications. Example: Any deviations in input material used from specification in agreement of sale. Table C List of Extra / Additiona/ Deleted Items considered in cost (which were not part of the original estimated of Total Cost) Sr. List of Extrイ Additionav Deleted items Amount (In Rs.) No。 Not Applicable